I have been following this forum for a while and finding everyone’s comments helpful as well being able to relate to most with regards to administration and building issues with Wisdom.
when we went through admin the time frames given by Wisdom are no where near the actual time it will take.
And to be honest you need to double any timeline given to you in admin and to what we are currently experiencing in construction.
We are 16 weeks into our contracted build period of 30 weeks.
Currently still only have approximately 1/3 of the brick work completed. Mind you the bricks have been on site now for close to 10 weeks.
In the 16 weeks of construction our site has had no action for approximately 8 of those 16 weeks.
The SS, when he bothers to give us an update, says the same excuse every time, the brickies are delayed, on another job etc.
We realise that because they certainly aren’t at our site.
He also said that he couldn’t possibly build our house in 30 weeks, we are looking at 40 weeks.
I reminded him of the contract build period that we signed and to that he said he was aware but it isn’t possible.
Be wary of the promised contract build period, as in our case there is no way the promised 30 weeks will be achieved even with the dry weather conditions we are experiencing.
At the rate we are going I am even doubting we will be at lock-up at the 30 week mark.
It is a case of over promise then under deliver.
Hi Bobby,
Welcome to the forum. We are experiencing the same through our construction so you are not alone. We are at the 21 week mark and only completed bricks last week however they did complete 90% of roof and eaves during the brick stage. Yes we also had periods of where it seemed nothing happened onsite. We also have a 30 week build period however I understand that it will be 40-45 weeks for my house. I'm being patient!
Good luck!