Hi All, I thought i would create a thread for our home, as I've seen so many amazing other ones, we are building with HGWA and are building a modified Monza in one of the new estates in Baldivis, we have been really impressed with the level of professionalism shown to us so far and they have helped us each step of the way, I have added a a photo of our home design, only other changes we will be making in prestart will be adding a door to the study, activity room and laundry in the scullery, we have also changed the sliding door to alfresco to a stacker door, I'm really big on doors and privacy, we want to eventually put a pool in so went for a more square shaped house and also wanted a big yard for our little one, we are really excited to start our journey and have a tile and laminate meeting booked for next week
Timeline so far
05/10/2017 - Selected Land
19/10/2017 - PCQ
22/10/2017 - Build Contract signed
24/10/2017 - Tile and Laminate meeting
01/11/2017 - Unconditional finance approval
22/11/2017 - Settlement
05/12/2017 - First docs completed
11/12/2017 - Prestart
20/12/2017 - Final Docs recieved
21/12/2017 - Final Docs returned
21/12/2017 - Entered Scheduling
09/01/2018 - Developer Approval received
07/02/2018 - Tap
09/02/2018 - Building Permit
09/02/2018 - End of Scheduling
14/02/2018 - Construction Email
16/02/2018 - Start of Earthworks
27/02/2018 - Slab down
10/03/2018 - Soakwells installed
12/03/2018 - Window frames delivered
13/03/2018 - Bricks and door frames delivered
19/03/2018 - Brickies commenced
22/03/2018 - Brick meeting with SS
26/03/2018 - Plate height - bricks completed
27/03/2018 - Roof frame commenced
04/04/2018 - Roof frame, eaves, fascias and gutters complete
04/04/2018 - Rough in for electrical and plumbing commenced
09/04/2018 - Roof Tin delivered
10/04/2018 - Roof Tin completes
10/04/2018 - Base render front of house
13/04/2018 - Windows and Glass doors installed
13/04/2018 - Dry wall installed
13/04/2018 - Gyprock for ceilings started
17/04/2018 - Cornice’s commenced, drywall flushed
20/04/2018 - Cornices completes
23/04/2018 - Drywall and Cornice Flushing sanded
24/04/2018 - Internal and Front door installed
24/04/2018 - Bath tub delivered
24/04/2018 - Lock Up
25/04/2018 - We get to seal our walls
30/04/2018 - Bath installed & waste pipe prep
01/05/2018 - Garage Poured
01/05/2018 - Ceilings and cornices painted
01/05/2018 - Doors and Frames under coated
01/05/2018 - Cabinetry delivered
03/05/2018 - Cabinetry installed
04/05/2018 - Stone installed
04/05/2018 - Tiles delivered
05/05/2018 - Floors being screeded
07/05/2018 - Wet areas waterproofed
10/05/2018 - Tile Meeting
10/05/2018 - Painting outside render
14/05/2018 - Tiling Commenced
22/05/2018 - Tiling Completed
24/05/2018 - Splashback installed
24/05/2018 - Plumbing finals - Taps installed
24/05/2018 - Electrical Finals
25/05/2018 - Ovens installed
25/05/2018 - Garage door installed
28/05/2018 - Ceiling Insulation installed
28/05/2018 - Hot water system installed
29/05/2018 - Pavers Delivered
30/05/2018 - Aircon Installed
01/06/2018 - Bathrooms Mirrors Installed
01/06/2018 - Mirror sliding doors installed
05/06/2018 - Painting Finals commenced
05/06/2018 - Front door stained
08/06/2018 - House Cleaned
09/06/2018 - Garage, Front and Back Eaves painted
09/06/2018 - Fly screens installed
09/06/2018 - Paving commenced
13/06/2018 - Carpet Installed
14/06/2018 - Paving Completed
15/06/2018 - Final Site clean
19/06/2018 - QCI
27/06/2018 - PCI
13/07/2018 - KEYS!