Browse Forums Building A New House Re: Who is building with Beechwood 1422Nov 01, 2011 7:20 pm Beechwood Homes Muscle Creek, Hunter Valley Paid Deposit Oct '10 Colour selec/Contract 17 Aug '11 28 days start- 12 Sept Bricks start 12 Jan Walk-through 12 April Re: Who is building with Beechwood 1423Nov 01, 2011 7:37 pm McKeachies Run, Aberglasslyn Deposit paid 11th April Land registered 6th June Land settled 20th June Colour selections and contract signed 5th August Commencement letter received 26th September Re: Who is building with Beechwood 1426Nov 02, 2011 9:32 am Beechwood Homes Muscle Creek, Hunter Valley Paid Deposit Oct '10 Colour selec/Contract 17 Aug '11 28 days start- 12 Sept Bricks start 12 Jan Walk-through 12 April Re: Who is building with Beechwood 1429Nov 02, 2011 9:35 pm Our Acreage Build The Lakeview Lodge - Beechwood Homes 01/04/10 YES 2010 - Deposit paid 23/09 - PCI CANCELLED 28/09 - PCI - will it happen.-18 months later 07/10/11 - ITS OURS..WOOHOO Re: Who is building with Beechwood 1432Nov 03, 2011 12:00 pm Beechwood Homes Muscle Creek, Hunter Valley Paid Deposit Oct '10 Colour selec/Contract 17 Aug '11 28 days start- 12 Sept Bricks start 12 Jan Walk-through 12 April Re: Who is building with Beechwood 1433Nov 03, 2011 8:26 pm OMG Jack - we were told we had to pay for an interim but the OC was included in the price, our finance company was ok to settle without a OC as long as we forwarded it to them as soon as we got it. since we did alot of things ourselves (drainage) after handover, we only just got a OC this week, we have been hanging for it as the council wouldnt give us bins without a OC. We are the same with trying to get BW to fix the things after handover. I cant believe there trying to charge you all this extra money. what a nerve Our Acreage Build The Lakeview Lodge - Beechwood Homes 01/04/10 YES 2010 - Deposit paid 23/09 - PCI CANCELLED 28/09 - PCI - will it happen.-18 months later 07/10/11 - ITS OURS..WOOHOO Re: Who is building with Beechwood 1434Nov 04, 2011 7:52 pm outside plumbing done... frames delivered and trusses all delivered too ... happy days building modified merlot with terrazza central coast 23 june 2011 - council approved 18 december 2011 - gyprock Re: Who is building with Beechwood 1435Nov 04, 2011 8:00 pm coastie 1 outside plumbing done... frames delivered and trusses all delivered too ... happy days Great news Coastie. Is outside plumbing next step after the slab? Our slab is due to be poured on Monday. Bit of bugger it was not done this week, plumber delayed us. We are off to Qld on Sunday for 9 nights. We were hoping to take our boys up to see the cement trucks. Will make a pleasant surprise when we arrive back. McKeachies Run, Aberglasslyn Deposit paid 11th April Land registered 6th June Land settled 20th June Colour selections and contract signed 5th August Commencement letter received 26th September Re: Who is building with Beechwood 1436Nov 04, 2011 8:50 pm yeh after the slab the plumber i think comes and digs all the trenches and lays pipes for all the down pipes and so on... dont ask me what the so on is tho.haha and after another week the frames will be delivered.. building modified merlot with terrazza central coast 23 june 2011 - council approved 18 december 2011 - gyprock Re: Who is building with Beechwood 1438Nov 05, 2011 1:37 pm Can anyone tell me...are you allowed to move in with an interim certificate or do u need to wait for final OC to live in the house. We hav been told the house should be finished by end of Nov but to get driveway done and final OC by xmas will be pushing it i think.. Our blog: http://durhamsadventure.blogspot.com Re: Who is building with Beechwood 1439Nov 05, 2011 3:10 pm Natandash, We moved into our last place with the interin cert Basically, they give you the interim cert with a list of things necessary to achieve the final cert. our last one was things like "landscaping, steps to the garage, handrail on steps etc" Building Beechwood Genesis Muscat (modified) Contract signed- April 19 Benching done- May 19 Piering done- June 27 Slab Plumbing- July 1st Slab poured- July 6th Frame finished- August 11 Re: Who is building with Beechwood 1440Nov 05, 2011 7:55 pm As we did all our our drainage (we did the connection from water tanks to the house and septic tanks to house) we only got interim as well, but really....we couldnt move in until all those things were complete were complete as we didnt have water Our Acreage Build The Lakeview Lodge - Beechwood Homes 01/04/10 YES 2010 - Deposit paid 23/09 - PCI CANCELLED 28/09 - PCI - will it happen.-18 months later 07/10/11 - ITS OURS..WOOHOO go upvc window frames ensure insulation under colorbond. not just sarking, lighter color roof also not sure if you have seen this viewtopic.php?t=5823 last couple of pages… 4 110808 Even if it's not being sub-divided and you want to keep it as Torrens title, you will still need to talk to a town planner or Council themselves, to see if they will allow… 1 11129 |