Browse Forums Building A New House Re: Masterton Homes - The new thread 1961Feb 21, 2011 3:56 pm Villina with Contemporary Facade + Alfresco *Demo 22/4/2010 *Pool 04/05/2010 *Released to Construction 24/05/2010 *Slab 29 June 2010 *Start of Frame 30 July 2010 - 21 Aug 2010 *Bricks started 14/09/2010 - 13/10/2010 *Roof started (Facsia) 15/10/2010 *Lock Up 10/12/2010 *PCI 18 Feb *Keys in hand 24 Feb *IOC 09 March 2011 My Thread: https://forum.homeone.com.au/viewtopic.php?f=31&t=39843 Re: Masterton Homes - The new thread 1963Feb 21, 2011 7:17 pm Building Masterton Villina - Contemporary in Forestville Paid $2500 - Oct 29 2009 Signed Contract - 22 Jan 10 Council submission - 31 Mar 10 DA Approved - 9 July 10 Slab - 5 Oct 10 Frame Delivered - 14 Oct 10 Bricks Started - 12 Nov 10 Bricks Complete - 6 Jan 11 Roof Complete - 20 Jan 11 Lock Up - 9 Feb 11 Re: Masterton Homes - The new thread 1964Feb 21, 2011 8:13 pm SunshineT's Build: viewtopic.php?f=31&t=34585 Designs start: 4/12/09 DA: 5/7/11 Demo: 22/12/11 Slab: 24/2/12 Keys: 31/8/12 Re: Masterton Homes - The new thread 1965Feb 22, 2011 8:43 am Building: Masterton Villina Savoy in the Sutherland Shire http://nathanandvivienbuildahome.blogspot.com/ Re: Masterton Homes - The new thread 1967Feb 22, 2011 12:52 pm Villina with Contemporary Facade + Alfresco *Demo 22/4/2010 *Pool 04/05/2010 *Released to Construction 24/05/2010 *Slab 29 June 2010 *Start of Frame 30 July 2010 - 21 Aug 2010 *Bricks started 14/09/2010 - 13/10/2010 *Roof started (Facsia) 15/10/2010 *Lock Up 10/12/2010 *PCI 18 Feb *Keys in hand 24 Feb *IOC 09 March 2011 My Thread: https://forum.homeone.com.au/viewtopic.php?f=31&t=39843 Re: Masterton Homes - The new thread 1968Feb 22, 2011 7:33 pm Building Masterton Villina - Contemporary in Forestville Paid $2500 - Oct 29 2009 Signed Contract - 22 Jan 10 Council submission - 31 Mar 10 DA Approved - 9 July 10 Slab - 5 Oct 10 Frame Delivered - 14 Oct 10 Bricks Started - 12 Nov 10 Bricks Complete - 6 Jan 11 Roof Complete - 20 Jan 11 Lock Up - 9 Feb 11 Re: Masterton Homes - The new thread 1969Feb 22, 2011 7:43 pm SunshineT's Build: viewtopic.php?f=31&t=34585 Designs start: 4/12/09 DA: 5/7/11 Demo: 22/12/11 Slab: 24/2/12 Keys: 31/8/12 Re: Masterton Homes - The new thread 1970Feb 22, 2011 7:51 pm SunshineT's Build: viewtopic.php?f=31&t=34585 Designs start: 4/12/09 DA: 5/7/11 Demo: 22/12/11 Slab: 24/2/12 Keys: 31/8/12 Re: Masterton Homes - The new thread 1971Feb 22, 2011 8:02 pm Building: Masterton Villina Savoy in the Sutherland Shire http://nathanandvivienbuildahome.blogspot.com/ Re: Masterton Homes - The new thread 1975Feb 23, 2011 1:55 pm For info on our build: viewtopic.php?f=31&t=43093 Built the McLaren by Dechellis - slab down 22 Feb - handover 30 Aug 2011 - and gardens finished 9 Dec 2012!! Re: Masterton Homes - The new thread 1976Feb 23, 2011 2:49 pm Villina with Contemporary Facade + Alfresco *Demo 22/4/2010 *Pool 04/05/2010 *Released to Construction 24/05/2010 *Slab 29 June 2010 *Start of Frame 30 July 2010 - 21 Aug 2010 *Bricks started 14/09/2010 - 13/10/2010 *Roof started (Facsia) 15/10/2010 *Lock Up 10/12/2010 *PCI 18 Feb *Keys in hand 24 Feb *IOC 09 March 2011 My Thread: https://forum.homeone.com.au/viewtopic.php?f=31&t=39843 Re: Masterton Homes - The new thread 1977Feb 23, 2011 5:02 pm Progress is good. Kitchen is in. I am hoping for handover by the end of March so we can move in over the school holidays. That is the plan anyway. Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Building Masterton Villina - Contemporary in Forestville Paid $2500 - Oct 29 2009 Signed Contract - 22 Jan 10 Council submission - 31 Mar 10 DA Approved - 9 July 10 Slab - 5 Oct 10 Frame Delivered - 14 Oct 10 Bricks Started - 12 Nov 10 Bricks Complete - 6 Jan 11 Roof Complete - 20 Jan 11 Lock Up - 9 Feb 11 Re: Masterton Homes - The new thread 1978Feb 23, 2011 7:38 pm Love the kithcen Chris&Emily, Congrats!! - what colour is it? Building customised Masterton Fernleigh contract 7 April level 1 July slab 19 July frame delivered 30 July frame completed 27 Aug 10 roof started/gutters 27 Sept bricks & render finished 27 Oct frame inspection 17 Nov viewtopic.php?f=31&t=41222&p=618417&hilit=fernleigh#p618417 Re: Masterton Homes - The new thread 1979Feb 23, 2011 8:35 pm topdeck Love the kithcen Chris&Emily, Congrats!! - what colour is it? Kitchen doors are Createc, Colour is Malt. Benchtop will be Luna White. We used the Masterton Colours consultant so hopefully everything will look good. At least my wife is very happy so far. Chris Building Masterton Villina - Contemporary in Forestville Paid $2500 - Oct 29 2009 Signed Contract - 22 Jan 10 Council submission - 31 Mar 10 DA Approved - 9 July 10 Slab - 5 Oct 10 Frame Delivered - 14 Oct 10 Bricks Started - 12 Nov 10 Bricks Complete - 6 Jan 11 Roof Complete - 20 Jan 11 Lock Up - 9 Feb 11 Re: Masterton Homes - The new thread 1980Feb 24, 2011 1:18 pm Awesome kitchen! Villina with Contemporary Facade + Alfresco *Demo 22/4/2010 *Pool 04/05/2010 *Released to Construction 24/05/2010 *Slab 29 June 2010 *Start of Frame 30 July 2010 - 21 Aug 2010 *Bricks started 14/09/2010 - 13/10/2010 *Roof started (Facsia) 15/10/2010 *Lock Up 10/12/2010 *PCI 18 Feb *Keys in hand 24 Feb *IOC 09 March 2011 My Thread: https://forum.homeone.com.au/viewtopic.php?f=31&t=39843 4 17234 Hi, Apologies - I know there is plenty out there on this but struggling to put together the puzzle. We're planning our garage/external laundry to master bedroom and… 0 12630 Hi there! Putting the feelers out there for those who have (or almost) built with Arli homes! Interested in your experiences who've built from their stock home designs… 0 26681 |