Browse Forums Building A New House Re: Masterton Homes - The new thread 1481Aug 23, 2010 2:35 pm Villina with Contemporary Facade + Alfresco *Demo 22/4/2010 *Pool 04/05/2010 *Released to Construction 24/05/2010 *Slab 29 June 2010 *Start of Frame 30 July 2010 - 21 Aug 2010 *Bricks started 14/09/2010 - 13/10/2010 *Roof started (Facsia) 15/10/2010 *Lock Up 10/12/2010 *PCI 18 Feb *Keys in hand 24 Feb *IOC 09 March 2011 My Thread: https://forum.homeone.com.au/viewtopic.php?f=31&t=39843 Re: Masterton Homes - The new thread 1482Aug 23, 2010 2:55 pm Masterton Santorini Grande 23/01/09 First Tender 17/11/09 Contract signed 25/01/10 Slab 27/03/10 Frame 7/5/10 Bricks 1/07/10 Roof 9/7/10 Lock up 24/8/10 PCI 16/09/2010 KEYS! viewtopic.php?f=31&t=16418 Re: Masterton Homes - The new thread 1483Aug 24, 2010 10:50 am Villina with Contemporary Facade + Alfresco *Demo 22/4/2010 *Pool 04/05/2010 *Released to Construction 24/05/2010 *Slab 29 June 2010 *Start of Frame 30 July 2010 - 21 Aug 2010 *Bricks started 14/09/2010 - 13/10/2010 *Roof started (Facsia) 15/10/2010 *Lock Up 10/12/2010 *PCI 18 Feb *Keys in hand 24 Feb *IOC 09 March 2011 My Thread: https://forum.homeone.com.au/viewtopic.php?f=31&t=39843 Re: Masterton Homes - The new thread 1484Aug 26, 2010 2:55 pm Masterton Santorini Grande 23/01/09 First Tender 17/11/09 Contract signed 25/01/10 Slab 27/03/10 Frame 7/5/10 Bricks 1/07/10 Roof 9/7/10 Lock up 24/8/10 PCI 16/09/2010 KEYS! viewtopic.php?f=31&t=16418 Re: Masterton Homes - The new thread 1486Aug 26, 2010 3:44 pm 1st Tender - 20 March 2010 Slab - 14 August 2010 Frames - 31 August 2010 Roof - 11 September 2010 Bricks finished - 2 October 2010 Lock up - 15 October 2010 Keys - 10 December 2010!!!!!!!!!!!!!!!!!! Thread: viewtopic.php?f=31&t=41002 Re: Masterton Homes - The new thread 1488Aug 27, 2010 10:41 am 1st Tender - 20 March 2010 Slab - 14 August 2010 Frames - 31 August 2010 Roof - 11 September 2010 Bricks finished - 2 October 2010 Lock up - 15 October 2010 Keys - 10 December 2010!!!!!!!!!!!!!!!!!! Thread: viewtopic.php?f=31&t=41002 Re: Masterton Homes - The new thread 1489Aug 27, 2010 12:38 pm Villina with Contemporary Facade + Alfresco *Demo 22/4/2010 *Pool 04/05/2010 *Released to Construction 24/05/2010 *Slab 29 June 2010 *Start of Frame 30 July 2010 - 21 Aug 2010 *Bricks started 14/09/2010 - 13/10/2010 *Roof started (Facsia) 15/10/2010 *Lock Up 10/12/2010 *PCI 18 Feb *Keys in hand 24 Feb *IOC 09 March 2011 My Thread: https://forum.homeone.com.au/viewtopic.php?f=31&t=39843 Re: Masterton Homes - The new thread 1490Aug 27, 2010 12:45 pm Villina with Contemporary Facade + Alfresco *Demo 22/4/2010 *Pool 04/05/2010 *Released to Construction 24/05/2010 *Slab 29 June 2010 *Start of Frame 30 July 2010 - 21 Aug 2010 *Bricks started 14/09/2010 - 13/10/2010 *Roof started (Facsia) 15/10/2010 *Lock Up 10/12/2010 *PCI 18 Feb *Keys in hand 24 Feb *IOC 09 March 2011 My Thread: https://forum.homeone.com.au/viewtopic.php?f=31&t=39843 Re: Masterton Homes - The new thread 1491Aug 27, 2010 1:19 pm Never argue with an idiot they drag you down to their level & then beat you with experience - Dilbert View Thread: viewtopic.php?f=31&t=19733 Contract signed 14Sept Slab 30Sept Bricks laid 1Dec Lock up 26Feb Keys 10Jun Re: Masterton Homes - The new thread 1492Aug 27, 2010 6:04 pm sabs1 FussyGirl Thanks BZMZ. So even though I will pick one colour for all the doors, skirtings and architraves it will cost me $275 plus $27 for each door? I can't believe it. I'm having a 40mm benchtop which is in our tender and a waterfall edge. But I'm prepared for the worst in terms of what choice I have with colours. I've also included carpet in our tender (standard builders range). Is this stuff any good? I will try and start my own thread some time soon. Hey Fussy Girl, welcome to the forum!! We also have the 40mm Benchtop with waterfall edge. I am still unsure if we made the right decision - there wasnt much of a choice... One thing that I would recommend : If you are going for a glass splashback then get another quote as ours was about $3K through M and we were so over it by that stage that we just accepted it. We went for the mid range Accent, not much of a choice there either. Thanks sabs1. We are going out tomorrow to look at colours so hopefully I will be better prepared for our colours day next week. FussyGirl First tender 5/3/2010 Contract signed 22/7/2010 Re: Masterton Homes - The new thread 1493Sep 02, 2010 11:07 am Hi everyone, we've been absent or quite some time now but for good reason. We had or baby girl on the 5th of July and she is just divine! we are living in a myriad of PINK! As a result of all our baby gazing our momentum stalled a bit but getting the ball rolling again. The DA for the Demo and the Pool are in and have had no objections. We have a verbal consent on the pool so that's good news! Now just to get the plans right and into council so that we can Demolish and get started before the end of the year! We have been really fussy with our plans being particular of the finer details. Which must be driving our consultant and his PA up the wall, but hey We ARE going to live in it! we are nearly there we are just waiting on a breakdown of the base price which we requested in June. I cant' understand why they are holding back on that. Will read through and have look at what everyone is up to! Building The Santorini Custom BA Signed 22/09/10 DA Approval 20/1/11 Demo 28/2/11 Pool 18/3/12 Slab 22/07/12 Frame 24/8/12 Bricks 7/09/12 Roof 19/10/11 Blog http://santorinidreams.wordpress.com/ Re: Masterton Homes - The new thread 1494Sep 02, 2010 11:43 am Congratulations sunny_and_warm!! What fantastic news!! We've have a few H1 babies recently, such wonderful news! sunny_and_warm We have been really fussy with our plans being particular of the finer details. Which must be driving our consultant and his PA up the wall I suspect that after a while it just becomes a job but I think they forget that for many of us, this will be the family home forever, or at least a very long time! You definitely need to be happy with it. Yay!! Babies!!!! (my babies just turned 3 and 5 so I am missing that delicious newborn stage terribly!!) Masterton Santorini Grande 23/01/09 First Tender 17/11/09 Contract signed 25/01/10 Slab 27/03/10 Frame 7/5/10 Bricks 1/07/10 Roof 9/7/10 Lock up 24/8/10 PCI 16/09/2010 KEYS! viewtopic.php?f=31&t=16418 Re: Masterton Homes - The new thread 1495Sep 03, 2010 4:36 pm MrsRose sabs1 Sorry Lizzy, no idea! Have you pm'd Mrs Rose - she is the GURU! Thanks I called DH to check on the power info and this is what he said... Masterton provides cable between house and pole, you need to pay an electrician (either masterton electrician or your own private one [cheaper]) to connect the supply between pole and electricity grid (they need to be category 3). They will connect the metering in the meter box also (only about $100). Your meters upgrade (is that for 3 phase?) is separate. The electrician (cat 3 one) can only do their job once Masterton has finished and certified their electrical work on the internals. Here is a list of people that provide the service (category 3 person) to do the work (connection from private pole to mains). http://www.fairtrading.nsw.gov.au/pdfs/ ... level2.pdf We got a much cheaper quote than the guys that Masterton use ($710 + GST incl metering, Integral Energy site inspection fees, labour and cable -v- $870 + GST from YHC). Hope this helps, Cheers Thanks Mrs Rose, as always, very useful information !! Villina with Contemporary Facade + Alfresco *Demo 22/4/2010 *Pool 04/05/2010 *Released to Construction 24/05/2010 *Slab 29 June 2010 *Start of Frame 30 July 2010 - 21 Aug 2010 *Bricks started 14/09/2010 - 13/10/2010 *Roof started (Facsia) 15/10/2010 *Lock Up 10/12/2010 *PCI 18 Feb *Keys in hand 24 Feb *IOC 09 March 2011 My Thread: https://forum.homeone.com.au/viewtopic.php?f=31&t=39843 Re: Masterton Homes - The new thread 1496Sep 03, 2010 5:59 pm sunny_and_warm Hi everyone, we've been absent or quite some time now but for good reason. We had or baby girl on the 5th of July and she is just divine! we are living in a myriad of PINK! As a result of all our baby gazing our momentum stalled a bit but getting the ball rolling again. The DA for the Demo and the Pool are in and have had no objections. We have a verbal consent on the pool so that's good news! Now just to get the plans right and into council so that we can Demolish and get started before the end of the year! We have been really fussy with our plans being particular of the finer details. Which must be driving our consultant and his PA up the wall, but hey We ARE going to live in it! we are nearly there we are just waiting on a breakdown of the base price which we requested in June. I cant' understand why they are holding back on that. Will read through and have look at what everyone is up to! Congrats on the bub! Any chance of a pic? Whats her name? So exciting!!!!! xx And you are right about being fussy with the finer details if I had a dollar for every time our consultant tried to tell us that it wasn't necessary and it ended up being necessary cause if it wasn't in the tender or plans our SS wasn't going to do it. Never argue with an idiot they drag you down to their level & then beat you with experience - Dilbert View Thread: viewtopic.php?f=31&t=19733 Contract signed 14Sept Slab 30Sept Bricks laid 1Dec Lock up 26Feb Keys 10Jun Re: Masterton Homes - The new thread 1497Sep 03, 2010 8:52 pm Hi Everyone, I've been following the thread for a while and reading all your posts with interest - we're also building with masterton, fernleigh 44 . We knocked down mid May, slab mid July, and frames completed 28 Aug. We were supposed to have the brickies arrive last Monday but apparently our SS's boss had a job which needed brickies urgently so they've been diverted off there (how rude - who's house is more urgent than mine i ask you) Anyway, just wondering whether anyone else is having problems getting brickies? Re: Masterton Homes - The new thread 1498Sep 04, 2010 1:34 pm Hi Topdeck, welcome to the forum. We have been waiting for bricks for 2 weeks and are hoping to get them next week. When the brickie will actually start is another question. They are in huge demand and I have been told that some are getting paid as much as $2.00 a brick. My guess is the M will not pay that rate so have to use the ones on existing contracts or aggreements. I am pretty sure we are waiting for the brickies that are doing another house in Concord. Good Luck! Lets hope that the rain goes away as I believe for every rain day, they need to wait up to a week before carrying on otherwise the bricks bleed or something like that... Villina with Contemporary Facade + Alfresco *Demo 22/4/2010 *Pool 04/05/2010 *Released to Construction 24/05/2010 *Slab 29 June 2010 *Start of Frame 30 July 2010 - 21 Aug 2010 *Bricks started 14/09/2010 - 13/10/2010 *Roof started (Facsia) 15/10/2010 *Lock Up 10/12/2010 *PCI 18 Feb *Keys in hand 24 Feb *IOC 09 March 2011 My Thread: https://forum.homeone.com.au/viewtopic.php?f=31&t=39843 Masterton Homes - The new thread 1499Sep 06, 2010 10:38 am Hi Guys, Has anyone ever made a major complaint to Masterton Homes or approached Mr Jim Masterton himself on the slowness and time they seem to take to do anything. We are building the Santorini and its taking forever to get a SLAB!! Our contract started on the 21st July. Is there anyone we can contact? They keep saying weather but today is an amzing sunny day and once again not a single person on site! I just want my house built for my wife and 2 young boys... Very Fustrated.... Re: Masterton Homes - The new thread 1500Sep 06, 2010 4:49 pm hey topdeck there is massive demand for brickies right now and everyone is slowing down in thie stage, they are mostly going to govenrment jobs where the pay is better, so depends on how quick your SS was in organising brickies prior to this, our neighbours who are building with eden brae went through the same thing aswell i believe Elizabeth estate - Schofields exchanged March 2015 4 17121 Hi, Apologies - I know there is plenty out there on this but struggling to put together the puzzle. We're planning our garage/external laundry to master bedroom and… 0 11726 Hi there! Putting the feelers out there for those who have (or almost) built with Arli homes! Interested in your experiences who've built from their stock home designs… 0 26428 |