Our contract is 167 days iirc, with 10 days of bad weather included and 42 for weekends/other delays. But if we end up at their close for Jan, its automatically extended by another 28 days.
So hopefully we're done ahead of that.
Browse Forums Building A New House Re: Our Places Fairhaven 23+ in Sandarra - Trussed 301Aug 04, 2010 2:36 pm Our Build - Places Fairhaven 23+ - https://forum.homeone.com.au/viewtopic.php?f=31&t=28045 Our Landscaping - Belial's Backyard - https://forum.homeone.com.au/viewtopic.php?f=19&t=45375 Re: Our Places Fairhaven 23+ in Sandarra - Trussed 304Aug 04, 2010 8:27 pm Our Build - Places Fairhaven 23+ - https://forum.homeone.com.au/viewtopic.php?f=31&t=28045 Our Landscaping - Belial's Backyard - https://forum.homeone.com.au/viewtopic.php?f=19&t=45375 Re: Our Places Fairhaven 23+ in Sandarra - Trussed 305Aug 04, 2010 8:41 pm Site Start - 20th July 2010 Slab Pour - 30th July 2010 Frame Start - 6th August 2010 Roof Tiles - 18th August 2010 Plaster Completed - 6th September 2010 Bricks - 3rd - 20th September 2010 Painting - 4th October 2010 Fitoff Begins - 21st October 2010 Re: Our Places Fairhaven 23+ in Sandarra - Trussed 306Aug 04, 2010 9:07 pm Our Build - Places Fairhaven 23+ - https://forum.homeone.com.au/viewtopic.php?f=31&t=28045 Our Landscaping - Belial's Backyard - https://forum.homeone.com.au/viewtopic.php?f=19&t=45375 Re: Our Places Fairhaven 23+ in Sandarra - Trussed 307Aug 04, 2010 10:06 pm Site Start - 20th July 2010 Slab Pour - 30th July 2010 Frame Start - 6th August 2010 Roof Tiles - 18th August 2010 Plaster Completed - 6th September 2010 Bricks - 3rd - 20th September 2010 Painting - 4th October 2010 Fitoff Begins - 21st October 2010 Re: Our Places Fairhaven 23+ in Sandarra - Trussed 308Aug 04, 2010 10:09 pm Our Build - Places Fairhaven 23+ - https://forum.homeone.com.au/viewtopic.php?f=31&t=28045 Our Landscaping - Belial's Backyard - https://forum.homeone.com.au/viewtopic.php?f=19&t=45375 Re: Our Places Fairhaven 23+ in Sandarra - Trussed 309Aug 04, 2010 10:17 pm Site Start - 20th July 2010 Slab Pour - 30th July 2010 Frame Start - 6th August 2010 Roof Tiles - 18th August 2010 Plaster Completed - 6th September 2010 Bricks - 3rd - 20th September 2010 Painting - 4th October 2010 Fitoff Begins - 21st October 2010 Re: Our Places Fairhaven 23+ in Sandarra - Trussed 310Aug 05, 2010 9:07 pm Our Build - Places Fairhaven 23+ - https://forum.homeone.com.au/viewtopic.php?f=31&t=28045 Our Landscaping - Belial's Backyard - https://forum.homeone.com.au/viewtopic.php?f=19&t=45375 Re: Our Places Fairhaven 23+ in Sandarra - Trussed 311Aug 05, 2010 9:18 pm Deemaree Kyndylan Capers: viewtopic.php?f=36&t=46852 My blog: http://www.sufficientlysufficient.blogspot.com/ Re: Our Places Fairhaven 23+ in Sandarra - Trussed 312Aug 05, 2010 9:26 pm Thread - https://forum.homeone.com.au/viewtopic.php?f=31&t=36205 Land Settled - 19 Jul Site Scrape - 23 Aug Slab - 2 Oct Frame - 27 Oct Locked Out - 1 Dec Handover - 11 Mar Re: Our Places Fairhaven 23+ in Sandarra - Trussed 313Aug 05, 2010 9:29 pm Our Build - Places Fairhaven 23+ - https://forum.homeone.com.au/viewtopic.php?f=31&t=28045 Our Landscaping - Belial's Backyard - https://forum.homeone.com.au/viewtopic.php?f=19&t=45375 Re: Our Places Fairhaven 23+ in Sandarra - Trussed 314Aug 05, 2010 11:19 pm way back in February standing on the slab felt great but perspective wise it will change for you when the frame happens - and when the plaster goes on - and when the paint is on the walls and again when the floors are in - I think my house keeps growing LOL as it looks bigger with each stage. Good luck Belial. p.s. keep an eye out as no one knows your house better than you and you may pick up an error early if you are 'stalking' like we were (our front junction boxes and portico light were in the wrong place but we told the builder and they were fixed just after they went in) Land: Titles 27/10/2009 - settled 9/11/2009 House Design: Talbot 28 (Contemporary Façade) Estimated move in date April 2010 ... ok maybe June 2010 with any luck Site Start 22/01/10 - 20/08/10 Handover!! Sandarra Facebook Group Re: Our Places Fairhaven 23+ in Sandarra - Trussed 315Aug 06, 2010 2:08 am Belial Janelle Your frame looks great, shame about the leaking roof Must be great to be able to walk through your framed house. I can't wait to be up to this stage. It makes a huge difference, its all a little hard to picture until you get that measure of scale. Still not too worried about the leak in the roof.... so long as it doesn't get any worse Hi Belial, ur frame looks great. Great pictures. We r also on framing stage at the moment but looks smaller not what we quiet expected. Hi Flame_on, house ur build going? Ur frame also looking great, am pretty sure it ur plot. Re: Our Places Fairhaven 23+ in Sandarra - Trussed 316Aug 06, 2010 2:11 am Belial Janelle Your frame looks great, shame about the leaking roof Must be great to be able to walk through your framed house. I can't wait to be up to this stage. It makes a huge difference, its all a little hard to picture until you get that measure of scale. Still not too worried about the leak in the roof.... so long as it doesn't get any worse Hi Belial, ur frame looks great. Great pictures. We r also on framing stage at the moment but looks smaller not what we quiet expected. Hi Flame_on, house ur build going? Ur frame also looking great, am pretty sure it ur plot. Re: Our Places Fairhaven 23+ in Sandarra - Trussed 317Aug 06, 2010 12:37 pm kbudgie way back in February standing on the slab felt great but perspective wise it will change for you when the frame happens - and when the plaster goes on - and when the paint is on the walls and again when the floors are in - I think my house keeps growing LOL as it looks bigger with each stage. Good luck Belial. p.s. keep an eye out as no one knows your house better than you and you may pick up an error early if you are 'stalking' like we were (our front junction boxes and portico light were in the wrong place but we told the builder and they were fixed just after they went in) Thanks guys, yeah keeping a good eye on everything, at the moment got a few items noted but we're taking a bit of a softly softly approach at the moment to see whether they are rectified in the course of work, rather than banging on about every tiny little thing. Hmm, way back in February.... I was trudging around in clay You guys got a PCI date yet? Couldn't be too far off? brianwijes Hi Belial, ur frame looks great. Great pictures. We r also on framing stage at the moment but looks smaller not what we quiet expected. Hi Flame_on, house ur build going? Ur frame also looking great, am pretty sure it ur plot. Hi Brian, Thanks we're quite happy with it and everything looks to be well put together. What do you mean, smaller than expected, have you actually got out a tape measure to make sure it all is to spec? Remembering that most plans mark the sizes to the frame (not the plaster). As for Flame_on, fairly sure that isn't his place iirc he's a couple of doors down from that one. Our Build - Places Fairhaven 23+ - https://forum.homeone.com.au/viewtopic.php?f=31&t=28045 Our Landscaping - Belial's Backyard - https://forum.homeone.com.au/viewtopic.php?f=19&t=45375 Re: Our Places Fairhaven 23+ in Sandarra - Trussed 318Aug 06, 2010 2:40 pm no official date yet but it may be next week if quality is checked and issues fixed between today and mid next week Land: Titles 27/10/2009 - settled 9/11/2009 House Design: Talbot 28 (Contemporary Façade) Estimated move in date April 2010 ... ok maybe June 2010 with any luck Site Start 22/01/10 - 20/08/10 Handover!! Sandarra Facebook Group Re: Our Places Fairhaven 23+ in Sandarra - Trussed 319Aug 06, 2010 3:01 pm kbudgie no official date yet but it may be next week if quality is checked and issues fixed between today and mid next week Sounds good, will be wishing you good quality and no faults . In other news, tried calling our SS and it diverted to the office, seems he has been taken to hospital (no other details were forthcoming) and so we've been re-assigned. So someone new to get to know. And in other news, having issues with our bank and paying our first invoice as they havent sent us out our authorisation sheets and hadn't taken into account all of our deposits thusfar despite the numbers at land settlement being correct. Our Build - Places Fairhaven 23+ - https://forum.homeone.com.au/viewtopic.php?f=31&t=28045 Our Landscaping - Belial's Backyard - https://forum.homeone.com.au/viewtopic.php?f=19&t=45375 Re: Our Places Fairhaven 23+ in Sandarra - Trussed 320Aug 06, 2010 5:51 pm Belial Sounds good, will be wishing you good quality and no faults . In other news, tried calling our SS and it diverted to the office, seems he has been taken to hospital (no other details were forthcoming) and so we've been re-assigned. So someone new to get to know. And in other news, having issues with our bank and paying our first invoice as they havent sent us out our authorisation sheets and hadn't taken into account all of our deposits thusfar despite the numbers at land settlement being correct. Thanks I hope your SS is ok and that the change does not cause you any delays (like you have not been waiting long enough!) and I hope the bank issues are resolved - all this is stressful enough!! Land: Titles 27/10/2009 - settled 9/11/2009 House Design: Talbot 28 (Contemporary Façade) Estimated move in date April 2010 ... ok maybe June 2010 with any luck Site Start 22/01/10 - 20/08/10 Handover!! Sandarra Facebook Group We are looking to do a KDR with fairhaven homes, Have seen plenty of good reviews about them pre construction and plenty of negative reviews about them during contruction… 0 18291 Hello everyone, I have a question regarding moving a chandelier after it has been mounted. The chandelier in question is quite large, measuring 4 meters… 0 72618 You have mandatory building inspections and privately engaged building inspections. The difference between the two comes down to inspecting the building so it's safe and… 3 18595 |