Browse Forums Building A New House Re: The McDonald Jones TULLOCH 31 - North Kellyville 13Dec 01, 2018 9:41 am We got the keys on the day before Easter Friday, about 120 days overdue (most of this was waiting for the Hebel to be erected, and the site manager not being on top of the contractors) Wonderful house, very few defects, but one that has become apparent is that one of the joists on the first floor (the one outside the master bedroom) has developed a very pronounced squeak, stairs also have some minor squeaks, but these don't matter so much. After Ross took over the site manager role things moved very fast. Re: The McDonald Jones TULLOCH 31 - North Kellyville 14Jul 09, 2019 8:05 pm arptel We are also building Tulloch 31 @ Riverstone, Next week is plan presentation appointment, Çan not wait to for it Hi, I am new to this forum and was looking for someone building tulloch 31 one. I have paid the initial deposit and waiting for the consolidated tender. Can you please share your experience and also how much did it cost approximately for the upgrades? I have a 10m frontage zero lot in schofields and hope there will not be any issues with the design approval from council? Please advise Regards, Charlie Re: The McDonald Jones TULLOCH 31 - North Kellyville 16Mar 12, 2021 5:05 pm NZ89 arptel We are also building Tulloch 31 @ Riverstone, Next week is plan presentation appointment, Çan not wait to for it Hi is it finished yet? Hey arptel, how is home Tulloch 31? 3 18717 Hi AKG, We had a base tender of $592 for 31 squares from MC Donald Jones. It looks relatively cheaper than other builders. But I assume there are many hidden things that… 1 13548 Hi i am looking to buy an investment near by North Rothbury. How is this area? is there schools inside this estate? please advice good builders around that area to buy… 0 1755 |