Browse Forums Building A New House Re: Who is building with Beechwood 11483Feb 08, 2016 11:17 am 30/01/16 - Site works commenced 02/03/16 - Piering completed 19/03/16 - Slab poured 06/04/16 - Frames completed 15/04/16 - Fascia/gutter/roof rail installed 20/04/16 - Roof tiles completed Re: Who is building with Beechwood 11484Feb 08, 2016 11:28 am Lexia Slim Twist with Beechwood Homes http://houseoflexia.blogspot.com.au/ https://www.instagram.com/natlyn7/ Re: Who is building with Beechwood 11494Feb 10, 2016 2:56 am Hi there, First time here and have read through a few pages. We have put in our specs for a fourth (and hopefully final) tender with BH at the Cooranbong office. We were told it would be back Sunday. Fingers crossed because I'm more than ready for this ball to be rolling. Looking forward to sharing our progress here and getting some advice ? Re: Who is building with Beechwood 11495Feb 10, 2016 4:32 am Verdelho5TGT Hi there, First time here and have read through a few pages. We have put in our specs for a fourth (and hopefully final) tender with BH at the Cooranbong office. We were told it would be back Sunday. Fingers crossed because I'm more than ready for this ball to be rolling. Looking forward to sharing our progress here and getting some advice ? How you finding the process? Why 4th tender? Is this before you paid the $5500 or after? Re: Who is building with Beechwood 11496Feb 10, 2016 5:53 am We settled on our 3rd tender. But it was us that changed things, not BH. From 1st to 2nd we removed the grand part of Terreza, and changed a few other things. Then from 2nd to 3rd, we added the grand Terrazza back. Since signing off on it and paying deposit we are now up to 3rd variation of 3rd tender. Which just included adding the tiles for grand back on which they accidentally left off (but this was a misunderstanding, not a fault), then extra provisional allowance for build and now waiting on 3rd for changing wooden pillions to brick piers to Terrazza. We did a day trip to Nowra yesterday and finally settled on bathroom/ensuite tiles. Now just waiting on confirmation on a few things and we are good to go once we have colour selection day. Hoping the 2nd round drawings come back this week and they are good to go to developer and CDC. (Once again changes we made not mistakes they did). We cannot fault our process so far. But not at building stage yet. Advise we were given by someone who has built 4 different houses with 4 different builders was to be patient. At the end of the day you get a beautiful house. Remember that they are a company building hundreds of houses not just yours. Something I think a lot of people forget. 20/11/15 - Settled land 06/11/15 - Request 1st tender BH 21/04/16 - Colour Selections and Contracts Signed 31/05/16 - Commencement Letter 24/06.16 - Started work onsite - cut and benching begun Re: Who is building with Beechwood 11497Feb 10, 2016 6:40 am Verdelho5TGT Hi there, First time here and have read through a few pages. We have put in our specs for a fourth (and hopefully final) tender with BH at the Cooranbong office. We were told it would be back Sunday. Fingers crossed because I'm more than ready for this ball to be rolling. Looking forward to sharing our progress here and getting some advice 😊 Im also very interested to know how your experience has been so far. Hope its been enjoyable for you Hey guys building a new place through a volume builder and just wondering if i should complain to the site supervisor as we just had plasterboard installed. Looks like… 0 11900 Elvis has left the building... The site supervisor quit after 2 month on the project. I guess he was just instructed to bark at people, but didn't like when he was… 26 21757 |