Browse Forums Building A New House Re: Building in Richmond SA - Lock Up 11th April 2013 141May 07, 2013 10:31 am Build thread: viewtopic.php?f=31&t=63784 Re: Building in Richmond SA - Lock Up 11th April 2013 142May 07, 2013 10:57 am Site Works 9/5/13 Slab 4/6/13 Frame 4/7/13 Fascia/Gutters 10/7/13 Windows 11/7/13 Roof 24/7/13 Gyprock 13/8/13 Lock up 26/8/13 Bricks 2/9/13 Kitchen 11/9/13 Tiling 28/9/13 Re: Building in Richmond SA - Lock Up 11th April 2013 144May 14, 2013 9:56 pm Deposit Paid 31/10/12 Selections 25/1/13 NHC 28/2 DCA 20/3 Siteworks 2/5 Slabbed 20/5 Wall Frames 3/6 Brickwork Finished 2/7 Lock Up 19/7 viewtopic.php?f=31&t=58864 Re: Building in Richmond SA - Lock Up 11th April 2013 149May 17, 2013 9:23 am Land Settled 2/11/11 Selections 24/9/12 Contract Signed 31/10/12 Site Works 17/1/13 SLABBED 29/2/13 Lock Up 11/4/13 PCI 22/5/13 Handover 3/6/13 http://w/w/w.project-buildahouse.blogspot.com Re: Building in Richmond SA - Lock Up 11th April 2013 150May 21, 2013 10:26 pm Deposit Paid 31/10/12 Selections 25/1/13 NHC 28/2 DCA 20/3 Siteworks 2/5 Slabbed 20/5 Wall Frames 3/6 Brickwork Finished 2/7 Lock Up 19/7 viewtopic.php?f=31&t=58864 Re: Building in Richmond SA - PCI Completed 22nd May 13 151May 22, 2013 5:16 pm Land Settled 2/11/11 Selections 24/9/12 Contract Signed 31/10/12 Site Works 17/1/13 SLABBED 29/2/13 Lock Up 11/4/13 PCI 22/5/13 Handover 3/6/13 http://w/w/w.project-buildahouse.blogspot.com Re: Building in Richmond SA - Lock Up 11th April 2013 152May 22, 2013 5:22 pm Miss Mia Good luck with PCI tomorrow, I doubt we would be able to sleep. Would be like Santa coming when we were all kids Make sure you give us an overview as to how it all goes and any valuable hints as to what to look out for !!!! Thanks Miss Mia! I must admit I had a hard time sleeping last night! Mainly out of excitement because we hadn't seen a lot of the finishing touches! Our SS was really easy going, he's been great throughout the whole process and really on the ball with things so we weren't anticipating any issues at all. I had read through our contract again this morning to refresh my memory and to also check a few things that we had noticed missing last time we went through and that did help us out. We had two things on our list that we thought could have been overlooked, the first being the fly screen that we had added to the front window which hadn't been installed last time we'd gone by and also the colour of the shelves in the linen cupboard. When we got there the fly screen was on it just needs to be stained and the linen cupboard was an oversight from our initial consultant who didn't write down what colour we wanted them but they are fixing it up without any drama's! Land Settled 2/11/11 Selections 24/9/12 Contract Signed 31/10/12 Site Works 17/1/13 SLABBED 29/2/13 Lock Up 11/4/13 PCI 22/5/13 Handover 3/6/13 http://w/w/w.project-buildahouse.blogspot.com Re: Building in Richmond SA - PCI Completed 22nd May 13 154May 22, 2013 5:35 pm Awesome who did you use for the inspection? Reasonable price? So was there nothing mentioned for the shelves anywhere may have to check mine Initial Deposit 28/09/2012 // Prelim Contract Signed 25/11/2012 Selections 21/1/2013 to 23/1/2013 // Contract Signed 22/2/2013 Site Start 21/5/2013 // Slabbed 30/5/2013 Re: Building in Richmond SA - PCI Completed 22nd May 13 155May 22, 2013 5:40 pm Gristy Awesome who did you use for the inspection? Reasonable price? So was there nothing mentioned for the shelves anywhere may have to check mine The selections mentioned the butlers pantry but because we added it to the linen cupboard in the pre-construction selections appointment the colour wasn't listed anywhere. So may be a good idea just to double check. Will send a PM re inspector Land Settled 2/11/11 Selections 24/9/12 Contract Signed 31/10/12 Site Works 17/1/13 SLABBED 29/2/13 Lock Up 11/4/13 PCI 22/5/13 Handover 3/6/13 http://w/w/w.project-buildahouse.blogspot.com Re: Building in Richmond SA - PCI Completed 22nd May 13 156May 22, 2013 5:46 pm AmyMumma23 Very beautiful Thanks we are very happy with how it's looking, I think I'm in love! Land Settled 2/11/11 Selections 24/9/12 Contract Signed 31/10/12 Site Works 17/1/13 SLABBED 29/2/13 Lock Up 11/4/13 PCI 22/5/13 Handover 3/6/13 http://w/w/w.project-buildahouse.blogspot.com Re: Building in Richmond SA - PCI Completed 22nd May 13 157May 22, 2013 6:09 pm Looks fantastic!! I love the stone benchtop and the beautiful tile choices! How exciting - not long now! Re: Building in Richmond SA - PCI Completed 22nd May 13 158May 22, 2013 7:01 pm Woo hoo, looking very swank Re: Building in Richmond SA - PCI Completed 22nd May 13 159May 22, 2013 7:39 pm Looks really grand. I'm so glad the process has been so smooth with excellent people working for you to make sure everything is perfect. Re: Building in Richmond SA - PCI Completed 22nd May 13 160May 26, 2013 8:07 pm I loved the saw cut pavers when i was at Urbans too.. hope i can find some tiles in similar style. Initial Deposit 28/09/2012 // Prelim Contract Signed 25/11/2012 Selections 21/1/2013 to 23/1/2013 // Contract Signed 22/2/2013 Site Start 21/5/2013 // Slabbed 30/5/2013 Wow I hadn't realised things had gotten that pricey in just a couple of years since I built, that is crazy with how much land is now costing if you aren't lucky enough to… 3 7136 yes it does, you've just not understood it. theres a difference. 4 5341 Your house should come in "as new" condition. It should be clean, and without stains 1 4579 |