We got a quote back from a builder and I need a hand understanding some
bits of it.
They said the soil is H1 but haven't done a soil test ,this is from the guy looking at it I guess and experience.
We have not paid or signed anything so I guess it's better than nothing until we get soil tests done.
It said, steel re-enforced concrete slab on compacted fcr sub base, what does this mean? Would this be ok with H 1 soil if it's correct?
Another thing I read about having a meter wide perimeter concrete to help stop slab heave, can you just make the house slab a meter wider or does it have to be seperate ?
Cheers
Somehow I put this in the wrong area, could it be moved?