Browse Forums Building Standards; Getting It Right! Re: Fixing Stage Inclusion question 4Nov 16, 2010 3:53 pm Is this for a progress claim? Brick clean can be one of the last jobs you do on a job Roof of the Porch should have been during roof cover? Roof pointing before handover - often roof companies drag their feet with this if the builder doesn't hold back enough money to get the to return. Fixing permanent external doors - often done at lockup, but if you've got expensive doors they don't want damaged then often done 2 weeks before handover. Tiling wet areas is usually after lockup and fixing, after the vanity cupboards are installed. bath, basins etc... is usually after fixings. Thanks for much mate. I see that you do cabinets before flooring. For timber flooring, for most parts it's fine because it's got base plates, and for door jabs you can… 7 11565 I'll look into different shower heads and ask the plumber about some engineering and see what he says. Thanks 2 9567 Plumbers 'can be' plumbers, made all the worse by self certification which the building surveyor invariably accepts as proof of compliance! The good thing is that you know know. 3 4872 |