Hi there, I’ve posted a job online and I’m getting all sorts of different quotes for labour and material costs.
I am hoping someone can offer me some guidance with the following:
1. If the materials I have worked out looks about right.
2. What sort of timeframe the job can be achieved in, say with two bricklayers. (Ie. 12 hours, 2 days, 3 days with 2 people or one full day with 3 etc)
3. What I should be expecting to pay for such a job.
4. What should I expect to pay a good bricklayer as a day rate.
The materials required have been calculated as follows:
MATERIAL: approx. $1200 (inc. GST) which consist of
• Concrete blocks x 125 (2/3rds are 390x190x190 and other 1/3 are 390x190x90)
• for mortar (10 bags of cement + 2 bags of lime)
• for footings (10-12 bags of cement)
• for cement to be poured into concrete blocks (12 bags of cement)
• steel rods for footings (16 rods: 300mm x 12mm)
• steel rods to be put through the cement blocks from top to bottom (16 rods: 2100 x 12mm)
Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅
Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅
Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅
Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅
Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅
Dimensions of the desired posts:
Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅