well our woes continue with this frustrating builder.
The latest issue is that our slab has been poured and when the frames were marked out where they go i noticed some of the drainage for the main bathroom was infact in the 4th bedroom.
turns out the plumber f$#&*d up the main bathroom plumbing by 450mm.
The site supervisor assures me that it is not a big problem, but from where i stand and the 1/4 million dollar investment i am putting in, it is a MASSIVE ERROR!
Has anyone else had this issue? was it resolved painlessly? Should we be chasing some sort of compensation?