Hi all,
Was wondering if anyone with experience would be able to give us a bit of advice on pouring a house slab in 2 seperate pours.
Had a brief chat with the formwork the other day and he metioned that our house slab possibly might be poured in 2 seperate days, he said the reasons were cause we had a 1.9 metre step down. So the top bit would be pourde first then the bottom bit 2nd. I have yet to ask our SS about this and the concrete is scheduled to be poured next week sometime.
Is this normal or should I be concerned? If it's ok what should I look out for?
picture of the stepdown