We have now signed our contract and I'm beginning to wonder about the bathroom tiling. I'm still happy with the selections but I wish now that we'd gone with more tiling on the walls.
I'm hoping that I can just buy more tiles (ordered so they're from hte same batch ) and just get the tiler to do a bit extra for a cashie....
BUT if the tiler refuses and just does the standard....can I get it done later? More rows of tiles above the standard or will it be weird?
I can go and change it all but I'll be slugged a variation fee.
Is the tiler likely to go for the extra work?
Can more tiling be added successfully later?
Should I just bite the bullet and suck up the cost to get the contract varied?
Suggestions advice on the best way to go please.....
Thanks,
Jo