Hi guys,
The attached pictures show waterproofing that has been applied at the floor of a shower in my bathroom. You can see the tile which has been laid already at the bottom.
When the contractor came to start this work @ 8am he had a bare cement render surface to start with. By lunch time he had tiles completely laid over this surface and the rest of the bathroom. The product used is Davco K10 green, and on reading the products instructions this goes totally against them as they state a minimum of 6-8 hours drying time over 2 coats. I feel like he has only done one coat (thin at that). Interestingly.... the entire 20L bucket left behind is empty (must have just had enough left from the last job?).
Also....should I be able to see cement still through the waterproofing membrane?
Opinions much appreciated as I am currently trying to cancel the contract I have with this company as I have lost confidence in their works.
http://imgur.com/hqdGfSO
http://imgur.com/Y4yUtCQ