Browse Forums Real Estate 1 Mar 01, 2010 1:12 pm Hi guys, We've just received approval from Stockland to extend our land settlement by 1 month. Has anyone ever needed to request a second extention for land settlement, and what are the chances of getting another extention approved? Not that we need another extention now, but just curious to know. 12 March 2010 - Land titles received 3 April 2010 - Signed building contract 14 April 2010 - Prestart 28 April 2010 - Loan approved 30 June 2010 - Slab completed 27 August 2010 - Brickwork completed 22 September 2010 - Roofing completed 30 September 2010 - Internal walls plastered 12 October 2010 - Lock Up 19 November 2010 - PCI 26 November 2010 - Handover 29 December 2010 - Moved In https://forum.homeone.com.au/viewtopic.php?f=31&t=32584 Hi, We have a single story MacDonald Jones house, on a waffle pod slab with steel frame. Are we able to build a second story extension? Other info is we are 900mm from… 0 8373 Hello Josh, This is Irving from PRIMA, we are a manufacturer of the staircase, railings, kitchen cabinets, windows, doors from China. If you have requirement to purchase… 0 5419 I would say both styles you have pictured are steel. The lower chord of the first pic would be a massive lump if made using timber considering the size of the rafters. If… 1 6103 |