Hi
The slab in my house has been cut without engineers approval and also passed by the inspector / RBS.
The slab had 3 bars as per the plan, highlighted and noticed the 3rd bar has been completely cut out, also this has happened in multiple other locations in slab. Along most walls the slab had been cut to fit steel frame, and majority of Metal bars visible from concrete and now not 3 bars only 2.
Is this something the inspector should have noticed? What long term effect will it have on slab? Slab obviously been designed with 3 bars and now only 2 along majority of walls.
Thanks.