Does builders margin apply to provisional sum ?
Page 1 of 1
It seems quite clearly stated in the contract builders margin is only applied to amounts that come in over the allowance however our builder has included a margin on amounts lower then the allowance amounts.
Ahhh!
I have had a builder quote a build price with excessive pc costs only to say it dos not matter because they only charge what the pc items cost and refund the difference. When quizzed about the builders margin I was told that does not change. In effect he was lining his pockets with builders margin making out he was going to do me a favour with a refund....
1) initial (retail) price of PC item + GST, let's say $100
2) then they charge their own margin on top, let's say 25%, so 100% turns into $125
3) then they charge their own GST on top, so the customer ends up with paying $137.5
Also, most builders never buy at retail price, most probably they will be buying with at least 10% discount to the retail price.
Related
3/09/2023
1
You talk about deletions, are they variations or PS and PC adjustments? pleas list them
8/06/2023
5
I've just built 3 stairs off a landing out the back and been told by the private certifier I need hand rails sorry tried to attach a pic but couldn't mine don't have sides…
20/09/2023
7
i had the my concreters concrete right up to the fence. I have pits all along my path, so the water tends to drain away from the house and into the pits. There's only one…