I can’t tell you based on legalities of contract, just based on my experience. I looked at my old lock up inspection report just to check.
The lower level was yet to be rendered.
The upper level render was completed while the scaffolding was up. My facade had 2 colors so second color/additional coat was done later as there was access for this to be done later.
Look around at local builds
I think you’ll find this is pretty common.
By the way- Are you having a private inspection with a building consultant for lock up stage?... if so you may as well ask the inspector.
If not.... maybe think again. It’s an important time build stage as much will soon be covered up.
Unless it somehow allows access into the dwelling without it
Related
3/10/2023
4
regardless, your contract stipulates a payments schedule and SOPA doesn't give provision to that scenario. Your contractual terms appear to stand. Hence get a lawyer, it…
9/10/2023
3
There is no reason why building contract reconciliation cannot be done prior to handover, if the builder won't do it get someone to do it for you. Why would you pay for…