Browse Forums General Discussion 1 Oct 10, 2018 10:23 pm Hi all, Wanting some advice on progress payment schedule for a complete new extension on a house that will cost $3-400k. I know this isn’t exact since the builder has just used rough %s and front loaded the earlier works but does it still seems reasonable? Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Thanks. Hi, We have a single story MacDonald Jones house, on a waffle pod slab with steel frame. Are we able to build a second story extension? Other info is we are 900mm from… 0 5839 nothing to do with salespeole. you'd do well to read and ccomprehend the post before bashing away at the keys with some negative comment again. 4 5061 regardless, your contract stipulates a payments schedule and SOPA doesn't give provision to that scenario. Your contractual terms appear to stand. Hence get a lawyer, it… 4 8956 |