Time line
14-Sep-17 | Deposit for land |
30-Jan-18 | Deposit for plantation homes "Seville 30" |
02-Mar-18 | Contract signed with plantation homes |
09-Mar-18 | Colour selection"Cosham Studio" |
21-Mar-18 | Electrical appointment |
28-Mar-18 | Covenant approval |
25-May-18 | Land registred |
11-Jun-18 | Land Settlement |
03-Jul-18 | Council Approval |
18-Jul-18 | Handed over to Construction team |
23-07-18 | Site cut |
01-08-18 | Slab |
04-08-18 First Floor Frame Finished
17-08-18 | Roof on |
29-08-18 | Electrical roughly in |
09-09-18 | Windows in |
09-09-18 | Air con ducting in |
09-09-18 | plumbing roughly in |
13-09-18 | brick work started |
13-09-18 | Internal doors, aircon duct marked out on floor |
23-09-18 Plastering commenced