I have started home and land package with Metricon Home Solution, After six month with sign contract they came with contract typo issue of mismatch of 20K AUD, It is totally document issue from there side, but now they are asking us to pay that amount to process. So any body came cross this issue or any solution for this
Thank you
Building New House with Metricon
Page 1 of 1
Thank you
I have started home and land package with Metricon Home Solution, After six month with sign contract they came with contract typo issue of mismatch of 20K AUD, It is totally document issue from there side, but now they are asking us to pay that amount to process. So any body came cross this issue or any solution for this
Thank you
Thank you
Id seek legal advice only and not forum opinions
janaka Unfortunately contract start delays on site favours the builder
If they haven't started on site then your
options are now pay the increase or they will terminate the contract. goodluck
If they haven't started on site then your
options are now pay the increase or they will terminate the contract. goodluck
Related
13/12/2023
0
Hi, First of all, thank you to this community for sharing your thoughts and opinions. We are in early days of our pre-contract stage for Metricon Doulton and we are…
29/01/2024
0
Hello All 🙂 We are planning to start our journey of construction our first home. We zeroed down on Metricon and henley homes based on design suitable for our lot and…
15/03/2024
0
We don’t live in VIC so want to know the exterior colours of Lumiere display so we can see it at the paint shop. Not building with Metricon so my request went…