What would be considered the halfway point for a two storey project home with a contract 40 week build (including 3 wk Xmas shut down)?
We are at about the halfway point time wise, and we have completed frames, facia and gutter. That's it. Hopefully roof later this week.
My SS won't give it to me straight regarding:
-how far behind we are
-whether there's any hope of meeting PCI date,and
-when we can now reasonably expect it to be completed
C U S T O M. C O R A L. B R O N T E. 43
http://forum.homeone.com.au/viewtopic.php?t=79581