Browse Forums General Discussion Re: Do We Have The Right To Refuse To Pay This? 2Apr 01, 2016 10:16 pm ~Shellby~ GJ Bridgewater 203 11/3/2016 - Site Work Started 29/9/2016 - Handover 142 Work Days 6 Work Days Over https://forum.homeone.com.au/viewtopic.php?f=31&t=80174 Re: Do We Have The Right To Refuse To Pay This? 5Apr 02, 2016 11:04 am Custom downslope build Build thread viewtopic.php?f=31&t=61873 Blog http://www.buildingroyalmanor.blogspot.com.au Re: Do We Have The Right To Refuse To Pay This? 12Apr 03, 2016 9:59 pm Refer to your contract but long story short you don't have a leg to stand on. The shame about building contracts (MBA/HIA) is it gives the builder the right to increase the price due to: "discrepencies or errors in the documents adjustments to provisional sums variations to unforseen circumstances" [Clause 9] As you can see the builder can adjust prices for several reasons. I would however ask the builder for proof of how he came to that figure. E.g. invoices. I think you're entitled to that at a minimum. Hi Mofflepop, I would recommend finding a building designer to prepare plans, they should design to your specified budget. The benefit is you can tender the project out… 9 20355 I'm putting a new floor in my kitchen, slate flagging on a standard concrete slab. I have allowed for a bed thickness of up to 20mm to accommodate the different… 0 17537 They using concrete or timber sleepers? Timber or steel uprights? Any drainage behind sleeper? 3 5831 |