Cutting the story short
My build is towards the finishing stage, but builder been extremely slow to finish off work .
Contract 165 days. Now is been 320 days.
Now he doesn't pick up my call, doesn't provide a schedule since 5 months ago by email or writing....(prob protecting himself for evidence as agreeing to complete job by certain date)
Now some work is outstanding , decking+ fence+ kitchen appliance.
Rang master builder, master builder just said to contact a construction lawyer which is prob faster. (Not very helpful, prob at this time of year,they are just looking forward the holiday break)
What should I do? Best way to push him along ? Lawyer is the way to go? Or will QBCC do something more than Master Builder.?
It's just that his ignorance to my call and sms and email is pushing me and my wife to the limit.
Anyone with experience with a bad builder and has a good solution outcome, please help .
Thanks