Hi All, Just wondering if anyone has built with Statesman/Hickinbotham and knows an average time from lock up until handover?
Carpenter is about to go in, all exterior is complete now, interior has been gyprocked/plastered etc. We are doing the flooring (except bathroom and laundry of course) and also the kitchen splashback after handover-surely that cuts back the time?? LOL
All paving, stormwater, rainwater connection ( we only have rainwater for supply), hot water service, driveway etc all being done after handover.
So they have doors, frames, kitchen, laundry, bathrooms x2, tiling, 2nd fix electrical, cornices and painting inside and out to go