Browse Forums General Discussion Re: CasaView Schofileds - Payment Terms? 7Aug 19, 2014 12:51 pm 30/01/16 - Site works commenced 02/03/16 - Piering completed 19/03/16 - Slab poured 06/04/16 - Frames completed 15/04/16 - Fascia/gutter/roof rail installed 20/04/16 - Roof tiles completed Re: CasaView Schofileds - Payment Terms? 9Jul 08, 2015 9:55 pm Building Casaview Denison 30 https://fortdenison.wordpress.com/about Re: CasaView Schofileds - Payment Terms? 11Jul 15, 2015 8:44 pm Building Casaview Denison 30 https://fortdenison.wordpress.com/about Re: CasaView Schofileds - Payment Terms? 13Jul 17, 2015 8:30 am Building Casaview Denison 30 https://fortdenison.wordpress.com/about Re: CasaView Schofileds - Payment Terms? 14Aug 09, 2015 10:20 pm Building Casaview Denison 30 https://fortdenison.wordpress.com/about I believe that liquidated damaged should be amount of actual loss to the owner from the delays. The issue in all of this is building industry lobbying and contributing to… 5 3451 regardless, your contract stipulates a payments schedule and SOPA doesn't give provision to that scenario. Your contractual terms appear to stand. Hence get a lawyer, it… 4 11876 There is no reason why building contract reconciliation cannot be done prior to handover, if the builder won't do it get someone to do it for you. Why would you pay for… 3 6690 |