Wish everyone a merry Christmas and. Happy new year and a great building experience.
I secured a 375 sq m lot in Heron Park Harrisdale.
Construction is going to start soon....
Any advise on construction and experiences of building with Commodore Homes and Heron Park will be highly appreciated.
Cheers!!!!
My titles are due in April, so some more time to go before action begins mate...how are things at your end?
Cheers!
My rep has been reasonably good so far, but we've run into some rough tracks regarding structural changes after receiving working drawings. Essentially a number of dimensions on the drawings were wrong and they were trying to charge us to rectify them.
After standing our ground they appear to have come to the party and I'm ready to book prestart.
Beyond this I'm reading good things about the company lately. Their base inclusions and prices seem pretty good value so we're also hoping for a smooth running build.
I'll be sure to follow your progress!
I will note the concern and ensure I take it up with them if it happens to me also.
All the best
Titles expected in May (Most likely June)
I am waiting for slab down, expected to happen in next week
Cheers!
How long ago did you do prestart? I just did mine 15/1 and they told me anywhere between 3-6months before slab down
Looking forward to following your build
Slab went down this week.
Pre- Start Finished from my side - 12th September
Commodore took another 1 and half months to complete pre start process - 31st October
Scheduling took another month- 2nd December
Slab Down - 15th Jan
Another month minimum before brick work can start.
thanks
Related
14/06/2023
1
Ask for references and speak to them. If they are defensive or try to avoid the request, walk.
14/12/2023
14
I would never build with Fowler homes. I built with them in 2021 and till date maintenance issues are pending. All their existing trades and businesses don't work with…