Browse Forums General Discussion 1 Sep 01, 2011 7:31 pm June 2010: Land Aug Tender + Deposit for Villina 41 Dec DA in Feb DA out Mar Construction Cert May Slab June Frame viewtopic.php?f=31&t=45643 Re: HELP! What happens when the builder doesn't follow the p 3Sep 01, 2011 7:49 pm The builder is not allowed to just "change" your front elevation without you signing a variation. Why have they changed it? Did they find that the way it is drawn on the plans is structurally impossible? Ask the builder what the reason is for changing the elevation, because if it is not a structural reason then it should definitely be corrected to the way it was shown on the plans that you signed. Unfortunately though, it does seem that you will have to weigh up which you prefer - fixing the elevation, or having a delay. As mentioned above, check out your legal options before approaching the builder so that you know exactly where you stand. The concreter will take and reuse. In my case I bought structural LVLs and scraped them back and used them as joists. 1 5153 Hi Mofflepop, I would recommend finding a building designer to prepare plans, they should design to your specified budget. The benefit is you can tender the project out… 9 20417 This is a very tight fit, I'm not sure if you'll be able to achieve what you've described. Would you consider accessing the separate toilet from the laundry? If so maybe… 1 11252 |