Browse Forums General Discussion Re: Does the builder need to know? 3Aug 02, 2011 12:18 pm Metricon Riva 33 - http://herlihy-riva.blogspot.com Site start 15/03/2010 - Handover 23/12/2010 9 months and 8 days (284 calendar days) from site start to handover Re: Does the builder need to know? 6Aug 03, 2011 8:18 am Metricon Riva 33 - http://herlihy-riva.blogspot.com Site start 15/03/2010 - Handover 23/12/2010 9 months and 8 days (284 calendar days) from site start to handover I had an old shower unit that broke on me and when I took it off, there were only 2 water pipes, instead of the normal 2 water pipes and a shower head pipe. S o I… 0 36939 I've just built 3 stairs off a landing out the back and been told by the private certifier I need hand rails sorry tried to attach a pic but couldn't mine don't have sides… 5 5710 There is nothing in the various codes and standards that puts this requirement on the builder to do. I think that is what you are asking. Don't waste time trying to get… 5 2408 |