Okay I have asked this before but my question wasn't too clear, so i am asking again hoping for some feedback..
I am building with Big M - we have a 16 week build time from site cut date to practical completion. Site cut date was 23/8/10 so my calander calculations 16 weeks from there they should be finished by 13/12/10
Is my thinking correct that we will be given the keys on 13/12/10 or is there any other hidden waiting weeks I need to factor in?
I would love them to be finished before that date - and given after the 16 weeks are up they have to pay us $300.00 a week you would think they would be....(maybe)
Because we are relocating I have asked if I can be notified if it would be completed by 13/12/10 but they advised they can not give me any indication...... Understandable, but would be so much help if they could!
Because we 10hr drive from our build we cant even see the progress which sucks big time the only updates we receive are from our SS whom isnt too big on the info. Its week 9 of the build and I know our house has been bricked, fittings have arrived and kitchen this week..........
If anyone out there has had any experiences re the building time or know of any hidden weeks I am not factoring in please, please let me know!!