Hi guys. Here is one for the sparkies.
I was talking with the BIL who is building the mother of all sheds and we were discussing power. Understanding that the trench has to be 60cms deep (will actually be 90cms due slope) in orange conduit,and knowing that sparkies hate trenching (especially about 30 metres of it) can I pre run electrical cable in the above mentioned conduit myself, leaving ample for connection at both ends for the sparkie to terminate. This will obviously save me a heap of cash in labour. I dont want to run the caonduit with string incase the string breaks whilst running the cable through.
If so, what cabling should I be running. The shed will have lighting and standard GPO's, with no rewuirement for three phase.