Browse Forums General Discussion 1 Apr 08, 2007 12:07 am Hi Everyone
I thought it would be good to get an idea of how long houses are taking to build around the country. If you have built or are building let us know! Remember to say the state and whether double or single storey! Regards Re: Average build times by state 4Apr 10, 2007 12:25 pm Construction started in August 2006 and we are about 6-8 weeks away now.
First council approval (planning) took ~5 months the second lot (development approval) took around 6 weeks. Purchased our land in December 2004 ![]() Adelaide, SA. Queensland 5Apr 10, 2007 6:19 pm Double storey in Brisbane.
plans with private certifier - 8 weeks construction started in June'06 and finished with the handover 16th November'06 one storey house normally takes ca. 3 months. However, the builder has always 100days to complete the dwelling plus all the rainy days, plus weekends etc... cheers kate An Not sure where you are up to in the build but if you are mid way and they install a new footpath now it could be damaged again. What I did with mine was to install a… 3 5385 ![]() Great question about home loans and savings. You have a solid plan for your renovation funds, but you want to ensure you understand your loan and offset account details. 10 29858 ![]() |