Hi there
We are contemplating using a Bondek Slab between the basement and the ground floor
Reason is for the ceiling height, we can't dig any deeper due to the site restrictions
If we use Posi-struts, the ceiling height will be 2.4m and we don't want it this low
I'd like to know if anyone has any idea of the formwork and steel fixing costs to form up this sort of slab
We have a crew that can pour it, or do you know what the going rate would be here in Melbourne for these 2 different types of construction methods
Any help is much appreciated!