I am repairing the downstairs of my flood damaged house. I am a pensioner and a widow, navigating the draft contract before signing. The builder has provided the below Progress Payment which seems top heavy... your thoughts are appreciated.
Deposit once Contract signed to book job in 10%
Electrical rough in 10%
Plumbing rough in 10%
Once demolition & removal of tiles in the
main house complete 20%
Once wall frames are straightened &
existing door jambs are out 10%
Once new door jambs are in and
plastering is up to the stage of cornice 20%
When fix out materials arrive to site 10%
When painting is complete 5%
Upon final completion 5%