My builder is claiming that electrical rough in can not progress until mains connection point is absolutely pinned down which we already are verbally aligned with CitiPower what the two options are on each side of the frontage.
The meter box is already in and site is marked out by sparkie where to put everything according to the plan.
It seems to me that the builder is stalling for time unless I am missing something?