wallyworld
Well that is quite a big difference 12 weeks and 30 weeks. We have been told an average of 22 week. IS that 30 weeks for a single storey? What are others experience time wise from slab down to handover? Our slab went down July 4th, 22 weeks gets us to beginning December, which is good, but earlier would be great and later not so good....
I'd love for it to be 12 weeks hmmm....
I'd love for it to be 12 weeks hmmm....
Ours was a total of 24 wks which included the christmas break of 3 wks so taking that out a total of 21wks from slab to getting our keys......we also have windows etc stolen just as bricking was due to start so we had no action for close to 4 wks waiting for them to be replaced, which would take it down to 17wks if that lil mishap hadnt of happened!!