I thought I would set up this discussion for anybody wondering how much is involved in getting Planning Approval & a Building Permit from you local council.
If you need help or require some guidance on this then I have all the info required for generally all councils in Perth.
I have just been through the process with City of Armadale
I'm in Mundaring Shire and soon to go through this. Any information would be helpful.
Not sure what stage you are at in regards to submitting to planning, see below
Have you obtained?:
BAL
Survey
Owner Builder licence
Soil Test
What is needed for Planning Approval
Posted & Soft copy
1. Cover letter & checklist outlining what you have enclosed in you application
2. Form 1 downloadable from council website
3. Copy of Certificate of title (land-gate website)
4. Fees payable for estimated construction cost
5. Site plans (1:200 3-4 copies) This includes survey, any retaining proposed
6. Elevations (1:50 or 1:100 3-4 A3 copies)
7. Floor plans (1:50 or 1:100 3- 4 A3 copies)
Health Department
1. Effluent design (leach drain or ATU)
2. Fees
Technical Services
1. Storm water catchment & disbursement design. (soak-wells rain water tanks etc)
2. Clearing of land or proposed landscape
3. Fees
Will you be submitting the dwelling as certified or Un-certified?
Can you recommend someone and do you know how much they charge?
This is who I used.....
Green Start Consulting http://www.greenstartconsulting.com.au/
Contact:
james@greenstartconsulting.com.au
Fast turnaround of plans (2 days)
$385 including GST
What you will need to supply for certified
1. Full street Address
2. Local Government Area
3. Site Survey
4. Final Working Drawings
5. Specifications (Standard building Specifications Can be purchased from him also $33)
6. Engineering Details/plans (can recommend someone for this)
7. Termite Protection details
8. Energy efficiency (can recommend someone for this)
Other Approvals Needed
1. Health department approval (Depending on where you are building ATU or Leach drain approval)
2. Planning Approval Letter/details
3. Contract value of proposed construction (may or may not need this)
let me know if you need any more help
Cheers
We have only created a sketch.
What do we do first? Planning approval, then working drawings, then Building permit or is it owner builder license? What is the recommended order of proceedings from sketch please?
Thanks for your help!
I will contact Green Start tomorrow
Can you recommend someone for:
Termite Protection /i suppose we need a quote or description with type of protection that will be used/
Energy efficiency
If you are electrician please PM me because i need someone for my project.
Cheers
Hi chalky
1.First you need Planning approval / i was told you need one if you are requesting variation of R-codes, http://www.planning.wa.gov.au/dop_pub_p ... _Print.pdf
i don't have any so i am going for Building Permit / you need owner builder license /permit/ before that
http://www.commerce.wa.gov.au/building- ... pplication
We are in a fire zone so Mundaring shire insists we do one.
As Dbenz said you will require scaled drawings before you can submit to planning. These need to be of a standard form a drafty.
You will need to obtain a building OB licence before you submit for a building permit. Try to leave this as the last thing you do before you submit to building department as the OB is only valid for 6 months this enables you to attach this with your building permit. To obtain a OB ticket it usually takes about 3-4 weeks.
PM for my email address!
Cheers
Can you recommend someone for:
Termite Protection /i suppose we need a quote or description with type of protection that will be used/ Unfortunately I can't supply info on this as my project will be concrete and steel and as standards say termite protection is not needed/also James @ green start advised me on this.
Energy efficiency Don Fleming Ecorate WA info@ecoratewa.com www.ecoratewa.com (for my project $230) all online and fast 2 day turnaround
If you are electrician please PM me because i need someone for my project. Will do!
Cheers
If you haven't done so already!
Grant @ Entire Fire Management is who I used cheapest and great customer service. You will require a fire management plan from local council for them to do the audit.
Cheers
We are on our way with BAL assessment and sketches. We hope to have our plans to shire next week.
relatively all the same, most councils have minimum requirements for planning & building permit applications
Cheers
I don't suppose you could post your planning approval sketches so we can see ow much detail is required?
can you pm with your email and I will send them.
Cheers
Related
25/04/2024
11
Hi VK, Think it's worth investing time in an Owner Builder course to equip you with basic knowledge on Australian Building Industry and its regulations. Also, I suggest…
5/09/2023
0
Hi all. Anyone know when the $11,000 limit was set in legislation for renovations in QLD? Ive been renovating for 5 years now and this was the limit back then. As we know,…