Sahara 40
Page 1 of 5
Mahesh
hi Hussain, we are about to build sahara 31. materials are being ordered now.
Mahesh
Mahesh
Hi Mahesh which suburb and estate are you building in? Thanks for replying we can share our experiences and dos and don'ts in here.
We are building in south-east Melbourne, which is Clyde .
Ours is smaller than you , but we definitely can share our experience.😊
Hi Hussain,
We are building in south-east Melbourne, which is Clyde .
Ours is smaller than you , but we definitely can share our experience.😊
We are building in south-east Melbourne, which is Clyde .
Ours is smaller than you , but we definitely can share our experience.😊
We got a big family and we consider this house for next 20 years. We made some changes to our plan like alternative alfresco which means kitchen and alfresco will be at one side and family + dinning at another. Which gives us one big massive open area.
Did you selected any upgrade?
That's the main structural changes we had.
In Terms of inclusion we added new mixes,sinks,taps,spa, CCTV prewire ,theater pre wiring etc..That's basic things people normally do I guess.
We have just cleared the land for the builder. Wetland looks good too.
We have just cleared the land for the builder. Wetland looks good too.
You got decent upgrades and structural changes more then us.
Thanks. Are you getting flooring from Henly or after hand over . We are planing to do the flooring and driveway after handover .
Yes but not driveway, as my friends advice to do after hand over.
Thanks. Are you getting flooring from Henly or after hand over . We are planing to do the flooring and driveway after handover .
Yes but not driveway, as my friends advice to do after hand over.
How much is your contract value till now?
Thanks. Are you getting flooring from Henly or after hand over . We are planing to do the flooring and driveway after handover .
How much is your contract value till now?
It’s 360k.but bank valued 355K.how about yours . ?
425 k
It’s 360k.but bank valued 355K.how about yours . ?
425 k
How is your construction going, does it effect with recent lockdown and what time frame henley is saying to handover your house as henley is getting busier.
They didn’t give me new time frame though. Basically construction has no effect by stage 3 lock down.
But there would be minor delay .
The slab was to be poured last Friday but now It will be done tomorrow. I was asked to let my private inspector
Know about that .Also weather can delay construction too .
How long your home to finish ?
Is your frame stage finished ?
Hi Mahesh
Yes we are at lockup stage now and yours ?
Good morning Hussain,
They didn’t give me new time frame though. Basically construction has no effect by stage 3 lock down.
But there would be minor delay .
The slab was to be poured last Friday but now It will be done tomorrow. I was asked to let my private inspector
Know about that .Also weather can delay construction too .
How long your home to finish ?
They didn’t give me new time frame though. Basically construction has no effect by stage 3 lock down.
But there would be minor delay .
The slab was to be poured last Friday but now It will be done tomorrow. I was asked to let my private inspector
Know about that .Also weather can delay construction too .
How long your home to finish ?
Yes weather can delay things, but next week looks good. My handover date is mid December.
Who is your private inspector. Want to do our fixing and completion stage to be inspect. We have not use them for previous stages as we got good reviews about henley workmanship.