Hi everyone,

My partner and I have signed our preliminary agreement and paid the $1850. Just curious as to how long everyone had to wait until they received their contract back from them?
amyelizabeth137
Hi everyone,

My partner and I have signed our preliminary agreement and paid the $1850. Just curious as to how long everyone had to wait until they received their contract back from them?

amyelizabeth137
Our experience has been that nothing happens in a hurry. After signing our preliminary agreement we went through the tender process an additional 2 times before it was close enough to correct and before we ordered contracts. Roughly 4 weeks between each process.

Our expectations have always been set high, but never delivered. Always takes longer than told.
mpricecs
amyelizabeth137
Hi everyone,

My partner and I have signed our preliminary agreement and paid the $1850. Just curious as to how long everyone had to wait until they received their contract back from them?

amyelizabeth137
Our experience has been that nothing happens in a hurry. After signing our preliminary agreement we went through the tender process an additional 2 times before it was close enough to correct and before we ordered contacts. Roughly 4 weeks between each process.

Our expectations have always been set high, but never delivered. Always takes longer than told.

That must be frustrating! They told us 4 - 6 weeks and we barely changed the floor plan so crossing our fingers we aren't mucked around too much through the admin process.
amyelizabeth137
mpricecs
amyelizabeth137
Hi everyone,

My partner and I have signed our preliminary agreement and paid the $1850. Just curious as to how long everyone had to wait until they received their contract back from them?

amyelizabeth137
Our experience has been that nothing happens in a hurry. After signing our preliminary agreement we went through the tender process an additional 2 times before it was close enough to correct and before we ordered contacts. Roughly 4 weeks between each process.

Our expectations have always been set high, but never delivered. Always takes longer than told.

That must be frustrating! They told us 4 - 6 weeks and we barely changed the floor plan so crossing our fingers we aren't mucked around too much through the admin process.

All I can say is do not set your expectations too high. We are still in the admin process and just when we think we are close to coming out the other side, something else crops up adding more time to resolve. If we had gone on the time-frames we had been offered along the way, our house would nearly be completed by now.
Related
2/11/2023
2
Coral Homes-can they shrink plans?

Building A New House

Ask the council if there is a chance of getting build over easement exemption. Sometimes easements are unused and 24cm is not all that much. Good luck. And yes any builder…

27/05/2024
2
Is it possible to get the Coral Homes Highlands 36 home?

Building A New House

Hi so sorry for the late reply. I already contacted them and they wouldn't tell me instead they tried to get me to talk to one of their home coordinators and I'm not…

14/12/2023
14
So many builders going bust, how's King homes/Fowler homes?

Building A New House

I would never build with Fowler homes. I built with them in 2021 and till date maintenance issues are pending. All their existing trades and businesses don't work with…