How many months or weeks it took to reach to lock-up stage once brick/roof-tile work has finished?
Normally no more than a week or two.
What else is usually left out of lock up once the roof is over?
Wow.. My supervisor told me 3 months🙄
Related
20/12/2023
1
Theft and Vandalism at lock up stage

General Discussion

sure. its the builders problem.

20/06/2023
1
Pre-construction stage- Variations taking 6+ weeks to comple

General Discussion

The fastest thing a builder will do is bank your cheque, those systems work perfectly with lightning speed, everything else is slow burn. Just the way it is.

25/03/2024
7
Job sequences in fixing and fit-off stage

Building A New House

Thanks for much mate. I see that you do cabinets before flooring. For timber flooring, for most parts it's fine because it's got base plates, and for door jabs you can…

You are here
Building ForumBuilding A New House
Home
Pros
Forum