BASE PRICE EXTENSION CHARGES AFTER 270 DAYS FROM METRICON
Page 1 of 1
My inquiry about the BASE PRICE EXTENSION CHARGES AFTER 270 DAYS FROM METRICON .If some one build with them and paid for base price extension ,My inquiry for how much they should charge or they charged after 270 days price lock. Did they charge until the land titled or the site start date.who gonna pay for delay from the Builder side.
Hi reader,
My inquiry about the BASE PRICE EXTENSION CHARGES AFTER 270 DAYS FROM METRICON .If some one build with them and paid for base price extension ,My inquiry for how much they should charge or they charged after 270 days price lock. Did they charge until the land titled or the site start date.who gonna pay for delay from the Builder side.
My inquiry about the BASE PRICE EXTENSION CHARGES AFTER 270 DAYS FROM METRICON .If some one build with them and paid for base price extension ,My inquiry for how much they should charge or they charged after 270 days price lock. Did they charge until the land titled or the site start date.who gonna pay for delay from the Builder side.
Definitely till official start date. They usually take 3 to 4 weeks once DA approval is received.hope this helps
Related
7/03/2024
5
Unless there were unforeseeable issues with the site, I dont think you should have to pay for contractors errors or poor planning. I'd probably try and be reasonable and…