This is our timeline so far and I will add to it as the build goes on.
17/08/2017- Cut and fill
19/08/2017- Gravel delivered for temporary driveway.
22/08/2017- Piers dug
23/08/2017- Pods delivered
25/08/2017- Slab poured
29/08/2017- Frames Delivered
04/09/2017- Wall Frames erected
05/09/2017- Windows installed + Roof trusses completed.
06/09/2017- Guttering and fascia installed + Roof tiles delivered.
07/09/2017- Safety rails fitted for roof tilers to commence.
11/09/2017- Sarking and battons installed.
12/09/2017- Roof tiles loaded up to the roof and installation of tiles began.
13/09/2017- Roof tiles complete.
18/09/2017- Ridge Capping complete.
19/09/2017- Pointing completed on roof + Bricks Delivered.
20/09/2017- Plumber onsite running waterlines to taps internal and external.
21/09/2017- Plumber onsite again and plumbing all roughed in.
04/10/2017- Still no one onsite, I called site supervisor and was advised there's a shortage of brickies ours is next in line.
06/10/2017- Bags of cement delivered assuming getting ready for brickies to begin next week.
09/10/2017- Load of sand delivered and 2 Courses of bricks laid around the entire house.
10/10/2017- Brickies on site, 1 section done and bricks moved around house into piles.
11/10/2017- Brickies onsite, bricking one section per day.
12/10/2017- Brickies onsite
13/10/2017- No one on site.
16/10/2017- Brickies on site again began laying bricks in alfresco.
17/10/2017- Brickies onsite all day, Alfresco done.
18/10/2017- Brickies onsite all day.
19/10/2017- Brickies onsite.
20/10/2017- Brickies onsite, Bricked front porch.
23/10/2017- Brickies onsite, half done the final section of wall on far side, Bricked pillar in alfresco and laid 2 courses for parapet out front.
24/10/2017- Brickies on site, Finished all the main walls and finished Parapet.
25/10/2017- Brickies on site, Front pillar, tops of alfresco, started external window sills.
26/10/2017- Bricks Complete + Air con installers running ducting, some electrical roughed in, eaves delivered.
27/10/2017- Eaves Fitted, Electrician on site, metre box installed.
28/10/2017- Bricks cleaned, all timber supports removed, gyprock and cornace delivered for alfresco.
31/10/2017- Remaining gyprock delivered.
01/11/2017- Commenced fitting gyprock.
02/11/2012- Plasterers installing gyprock, day2.
03/11/2017- All wall and ceiling gyprock sheets hung. Front pillar and parapet rendered.
06/11/2017- Plasterers completed 1st coat of plaster on all walls and ceilings.
07/11/2017- Plasterers onsite again.
08/11/2017- Began waterproofing in ensuite, Laundry and main bathroom.
09/11/2017- Half of cornice done + more waterproofing.
13/11/2017- Cornice all complete.
14/11/2017- Door frames and internal doors delivered, Lock up today, kitchen, vanities and bath delivered.
15/11/2017- Sanded plaster.
16/11/2017- Garage door installed and kitchen installation started.
17/11/2017- Kitchen overhead cupboards installed. Laundry, bathroom and ensuite cabinetry installed.
22/11/2017- Kitchen benchtops installed, skirtings fitted to half the house and half the doors hung. Tiles also delivered.
23/11/2017- All internal doors hung skirtings complete, architraves nearly finished.
27/11/2017- Eaves painted, screeds laid, panelling installed above garage door.
28/11/2017- tiled laundry floor, bathroom floor ensuite floor and most of front patio.
04/12/2017- Painters onsite all windows and doors masked up can't see what was done.
06/12/2017- Painters onsite, ceilings sprayed 1 coat.