I have been stalking everyones threads for ages and figured I might as well start my own.
Thanks B
Timeline:
27 July 2016: Deposit paid on land
22 Oct 2016: Deposit / Preliminary Agreement signed Coral Homes
22 Feb 2017: Land registered
SaveSave
10 Mar 2017: Tile Appt/ Selections
11 Mar 2017: Contracts signed (with variations to come)
14 Mar 2017: We own some land!
31st Mar 2017: Colours Selection
11th April 2017: Electrical Appt online
Rest of April waiting .......
May waiting ...........
June (waiting on Coral regarding driveway placement (2 months) retaining wall (1month)
June spoke directly to Corals Private Certifier who are more than happy to request our retaining wall closer to boundary fence - when Coral have been telling us its not possible) - they also have told us they have only had our plans since June, Coral told us our plans were with them back at the end of April.
July waiting......
August waiting.........
26/09/17 Site cut and port loo !!!
Week One:
28/09/17 Piering & more fill over retaining
30/09/17 Retaining completed
Week Two:
3/10/17 plumbing /drainage fit out
6/10/17 slab frame up
Week Three:
12/10/17 slab pour
16/10/17 site clean up
Week Four:
18/10/17 coral signage up
20/10/17 frames & roof trusses delivered
Week Five:
24/10/17. Frames up
25/10/17 Roof trusses on
Week Six:
31/10/17 Scaffolding
1/11/17 Fascia and gutters on - tiles delivered
3/11/17 Sarking completed, Windows and Sliding Doors delivered
6/11/17 Roof started
Week Seven:
7/11/17 Roof completed
7/11/17 Bricks and cement delivered
8/11/17 House wrapped
9/11/17 Bricks started
Week Eight:
15/11/17 Bricks completed
15/11/17 Electrical rough
14/11/17 Internal plumbing
20/11/17 Frame inspection Coral & Private
20/11/7 plaster boards & cornices delivered
Week Nine:
23/11/17 Internal walls
25/11/17 Cornices
27/11/17 Bricks Acid washed
Week Ten:
30/11/17 Front rendered
30/11/17 Waterproofing
4/12/17 Indépendant Inspection
Week Eleven:
7/12/17 Front door on, internal doors hung, skirting carpeted areas and architraves completed
8/12/17 shelving Wardrobes and WIL completed
Week Twelve:
15/12/17 Wood Panelling Portico
15/12/17 Kitchen and Vanity cupboards delivered
18/12/17 Kitchen cupboards and all vanities in
Xmas Shut Down.....
Week Thirteen:
Bath and tiles wet areas delivered
16/01/18 Painting Started internal and external
Week Fourteen:
24/01/18 Wood area stained, and Eaves and render painted
27/01/18 Stone bench tops in
Week Fifteen:
29/01/18 Tiling commenced wet areas
30/01/18 Splash back tiled
1/02/18 painting completed
Week Sixteen:
nothing
Week Seventeen:
16/02/18 plumbing fitout, shower heads, taps and toilets in (laundry & kitchen not completed)
Week Eighteen:
19/02/18 Electrical fitout, all light switches, downlight, lights and fans in
20/02/18 IT bench in
22/02/18 Garage door raised
Week Nineteen:
2/03/18 Kitchen sink fitted in (stone cut)
Week Twenty:
(garage door fitted / shower screens- Didn't happen)
proposed 6/03/18 Carpenter finish doors, handles final finishes (postponed until 12th March)
scheduled 7th House clean - NO CLEANING!!!!!!
8th & 10th March Laminate Flooring
12/03/18 Carpets laid
Week Twenty One:
13/03/18 Carpenters fitted skirting, door handles
13/03/18 Vanity mirrors fittted, Shower screens in, Wardrobe doors in
scheduled 15th flyscreens
Week Twenty Two:
23/03/18 garage door on
Week Twenty Three:
27/03/18 Fences down, site partially cleaned
28/03/18 Flyscreens on
House siliconed
Week Twenty Four:
plumbing near Garage finally fixed, toilet removed
5/4/18 Main Audit HO
WeekTwenty Five:
9/4/18 Pendants Hung, kitchen, dining, bedroom
Week Twenty Six:
Week Twenty Seven:
Week Twenty Eight: END OF CONTRACT 216 DAYS since build commenced!!!!!
Post Contract Variations (for our records)
#1 3/04/17
#2 1/06/17
#3 13/04/17
#4 3/05/17
#5 26/07/17
#6 17/08/17
#7 18/08/17
Facade: St Kilda
Roof: Bristle concrete Classic Profile: Gunmetal
Brick: PGH Foundations Stone
Mortar: off white / ironed
Gutters / Fascia: Basalt
Eaves: Surfmist
Main Render: Surfmist
Piers: Shale Grey
Portico Timber: Walnut
Garage Door: Seville profile Basalt
Front Door: XS26 1200mm walnut stain
Windows / Sliding doors: AGL surfmist
Alfresco Posts: walnut stain (upgrade)
Watertank: Dune
Down pipes / Electrical box / External Garage door: Natural Wool
Piers: Stacked Stone at a later date
Kitchen:
Benchtop: Caesarstone 20mm Fresh Concrete
Cabinetry: Laminex Ghostgum
Feature Shelf Island: Laminex sublime teak
Ensuite/Bathroom/Laundry
Benchtop: 40mm Caesarstone Osprey
Cabinets: Laminex Sublime Teak
Interior paint:
Walls: Dulux Highgate
Trims / Doors: Dulux white on white (aqua enamel)
Flooring:
Classic 1050 Laminate: Spotted Gum
Carpet: standard range grey(name??) with 10mm upgraded underlay
UPGRADES:
External
Provide brick infills above all external doors doors $570
Increase height of garage door $370
Trilock Entry door handle $418
Stained timber posts to Alfresco $200
upgrade roof tiles to Bristile "classic" (shingle profile) $761
Push out bedroom 3 to eaves and relocate robe to laundry wall $759
Increase length of house 500mm $2844
Increase Length of Alfresco by 3680mm $5211
Provide external door to garage $300
Entertainer stacker to dining room door $300
Increase size of Master bedroom Window from 18-09 to 18-15 $135
Decrease Ensuite window from 21-09 to 21-06 -$17
Change location, type and size of bedroom 3 window from 18-09 to 15-18 $-$60
Change size of bedroom 4 window from 18-12 to 15-18 -$231
Option "D" chosen for ensuite $2999
Timber look floor upgrade $2499
Supply Carpet $1499
Kitchen upgrades $0 earlybird promotion
Appliance upgrades $999
Ensuite upgrades $1999
Bathroom upgrades $1999
High Ceilings $2250
Street Appeal upgrade $499
INTERIOR
Kitchen:
upgrade to deluxe stone island $265
Increase Pantry size 500mm -$20
Shelves to island $407
Shelves to be timber laminate $199
Pot drawers, two banks of three $894
Bronze range drawer handle $108
Clark Quatro 1.75 sink $770
Phoenix Blix mixer $188
Delete pantry shelving
Relocate fridge space and increase to 1000mm
Add single LIN 1 door to pantry with translucent glass $329
Wet areas:
Chrome waste to laundry $233
Change linen in laundry to broom cupboard -$227
Provide built in cupboard under laundry sink and laminated bench top $492
Decrease ensuite to be in line with WIR
robe hooks x 2 in ensuite $78
Metal chrome shelf to shower in Ensuite $121
Hand towel rings to ensuite and bathroom $37ea
Woodgrain laminate to ensuite and bathroom vanities $118
900mm double towel rail in bathroom $16
Luna wall faced toilets
Posh Solus free standing bath $448
Other items
Flyscreens $704
Secure view to sliding doors $2725
Underlay 10mm $336
We also paid more for the laying of some of our wet area tiles due to rectified edges (feature wall tiles only)
Think this is everything but please feel free to ask or message if theres something you would like to know that I haven't included.
Week One: Piering
Retaining by us
SaveSave
SaveSaveSaveSaveSaveSaveSaveSave
Week Two:
Plumbing
Slab frame up
Week three:
Slabbed and site clean up
Week Four:
Frames & roof trusses delivered Coral Signage up
Week Five: Frames and Roof Trusses up
Week Six: Scaffolding up gutters and fascias on, roof tiles delivered, sarking completed
SaveSave
Week Seven: Roof tiles laid, bricks delivered
SaveSaveSaveSaveSaveSave
Week Eight: Bricks completed and Electrical rough In
SaveSaveSaveSaveSaveSaveSaveSave
SaveSave
SaveSave