KDR With Rawson Homes - Balmoral 34 Mk1 - Majestic Facade
Page 1 of 6
Just thought I'd start sharing.
24-03-2016 Moved Out
29-03-2016 Gas Abolished by Jemena.
04-04-2016 Demo Begins (Democorp), Rawson SS assigned, but I don't know who it is. Edit: (Had I bothered to read the attached letter I would have seen who my SS is)
11-04-2016 Demo Complete. Awesome job by Democorp, they are a class act and I would highly recommend them.
13-04-2016 SS picked up file from Head Office.
14-04-2016 Clearance Certificate Received and forwarded to Rawson
19-04-2016 Peg Out Done
20-04-2016 Rawson Fencing is up
21-04-2016 Met with SS on site to go over any questions we might have about the process.
02-05-2016 Scraping in progress.
05-05-2016 Screw Piers installed.
09-05-2016 Under slab plumbing.
12-05-2016 Waffle Pods and reo.
16-05-2016 Slab
23-05-2016 Frames Delivered
29-05-2016 Windows Delivered
30-05-2016 Framing Started
07-06-2016 Framing and Windows Level 2
08-06-2016 Framing Completed
25-06-2016 Bricks Arrived
11-08-2016 Brickwork Complete (7 Weeks from arrival)
20-08-2016 Gutters, Fascia and roof completed
14-10-2016 All cladding done. Scaffolding removed. Electrical and plumbing rough in complete.
04-11-2016 Plasterboard and Waterproofing done
21-04-2017 Handover
Day one, Democorp on site bright and early. Wasting no time getting into it.
Good luck with your build. Isn't it exciting to get started?
Rawson Benham KDR
<URL>https://forum.homeone.com.au/viewtopic.php?f=31&t=82770&p=1531839#p1531839</url>
Where are you building? Looks like we might be on a similar timeline - our demolition is done and site excavation was completed last week. We're expecting slab pour in about a week and a half.
Good luck with your build. Isn't it exciting to get started?
Rawson Benham KDR
<URL>https://forum.homeone.com.au/viewtopic.php?f=31&t=82770&p=1531839#p1531839</url>
Good luck with your build. Isn't it exciting to get started?
Rawson Benham KDR
<URL>https://forum.homeone.com.au/viewtopic.php?f=31&t=82770&p=1531839#p1531839</url>
Thanks! Building in Rockdale. Demo should be done Monday. Can't wait to hand over to Rawson.
Good luck with your build!
Hi Joamoa, are you building front of side entry?
Front Entrance like CalvinHobbs. Very similar floor plan.
Joama - congrats on the start. We are building a balmoral too, will be watching with interest!
Thanks! What stage are you at? Do you have a thread here?
Won't hold my breath - as this will be the third start date they've given us
Haven't started a thread yet - hoping to do it once the build actually starts...
We've been assigned a new SS so I'm hoping he will get things moving
Yes they took possession quite a while ago with fences going up week or two before Easter long weekend (when they were first going to start)
We've been assigned a new SS so I'm hoping he will get things moving
We've been assigned a new SS so I'm hoping he will get things moving
Well at least the clock is ticking for them at this point, not you. Not much of a consolation, I know. At least it's been dry so they can't claim weather if they run over 10 months.
Best of luck.
Though not sure how clear I was that they have broken the contract - they should have started 20 days from peg out but tomorrow is about 33 days...
I'm not seeing any posts where people are ahead of schedule - preparing myself for frustration in the months ahead and trying to stay focused on the end game.
Rawson Benham KDR
<URL>https://forum.homeone.com.au/viewtopic.php?f=31&t=82770&p=1531839#p1531839</url>
All the best!
Hi Joamoa, are you building front of side entry?
Front Entrance like CalvinHobbs. Very similar floor plan.
Congratulations and good luck with your build! Take lots of photos throughout the progress!
I think Rawson have a personal development plan I wasn't aware I'd paid for - practicing patience . I will certainly be practising and trying to imagine just how good it will be when we are in
All the best!
All the best!
LOL. In all seriousness, just look at the bright side if you can. Once you sign the contract, the only thing you can do is always keep them in check. Think like honing your project management skills - it's your house and your money only you hired someone else to do these for you, but at the end result is a house they'll turn over to you once it's built.
Related
21/09/2023
0
Hi, I am looking into doing a KDR in Melbourne and am contemplating using Kialla Homes. I am looking for feedback on them from others who have built with them.
24/02/2024
0
Just started the Build process for Chifley 42 with Rawson homes, will keep you all posted with the Build progress.