8 March OTP block
22 May BT contract signed
23 May BT Pre start
11 June Settlement
1 July Final plans
7 Aug Slab Down
21 Nov Bricks complete
4 December upper slab poured
11 December upper frame work commenced
22 December upper frame & EPS cladding complete
3 January upper walls rendered
16 January upper roof colorbond finished
17 January upper wall Acratex applied
23 January scaffloding down
16 Feb lower roof timber commenced
20 Feb lower roof timber complete
25 Feb lower roof guttering commenced & sparky commenced
3 Mar lower roof colorbond complete & plumber started
6 Mar plumber & sparky first fix complete, internal wall float started
11 Mar internal wall float complete, aircon ducts in & white set commenced
17 Mar white set complete
19 Mar insulation bats started & plasterboard delivered
28 Mar Plaster Boarding commenced
11 April glazing fitted
15 April locked out (no front door)
19 April stairs in
23 April bath hob & shower nib walls in, wet floor screed
24 April internal doors & wardrobe fitout
1 May kitchen fitting commenced
11 May bathroom floor tiling started
13 May decorator started, he's not happy as he has some plastering issues
14 May bench tops in, kitchen bench not secure
24 May wall tiling progressed & decorating continued
3 June aircon install completed & front door fitted
23 June electrical & decorating progressed, tiling still not finished & garage floor grano layed
6 July internal clean and plumber fitted toilets sinks etc, water leak in laundry
9 July Colorbond fencing started
10 July water leak in laundry is terminal, not good news
11 July outside paving and internal plastering finally finished, boundary wall completed
15 July Week 49 PCI
31 July Week 51.................keys ..................at last
Quote:
they must be doing something right given the amount of BT houses in such a small area, hope they keep it up.
Hopefully you get a smooth run!
Following
Welcome Druid1, about time you started your thread. Looking forward to seeing your house develop.
Following
Following
Thanks Triggy, walked past your house yesterday, but couldn't decide which one was yours as there are so many by your builder to choose from, are you at lock up yet?
Welcome Druid1, about time you started your thread. Looking forward to seeing your house develop.
Following
Following
Thanks Triggy, walked past your house yesterday, but couldn't decide which one was yours as there are so many by your builder to choose from, are you at lock up yet?
Not yet. I'm the poor cousin in the middle of the 2 story and the Content one that's at lock up.
Welcome Druid1, about time you started your thread. Looking forward to seeing your house develop.
Following
Following
Thanks Triggy, walked past your house yesterday, but couldn't decide which one was yours as there are so many by your builder to choose from, are you at lock up yet?
Not yet. I'm the poor cousin in the middle of the 2 story and the Content one that's at lock up.
Are you backing onto bush land with a funny shaped block, which gives you a huge back garden, none of your photos in photo bucket link work.
Not yet. I'm the poor cousin in the middle of the 2 story and the Content one that's at lock up.[/quote]
Are you backing onto bush land with a funny shaped block, which gives you a huge back garden, none of your photos in photo bucket link work.[/quote]
Yep thats us. We are supposed to be down sizing on land and house but DH didn't want to go smaller than 520m2 and it was all that was available at the time as the sale had fallen through for the original buyers. So we have ended up on a larger lot, a triangle 628m2 but with a smaller house. The garden is going to be mostly pool, pavers and astroturf. I hate gardening.
Thanks Triggy, walked past your house yesterday, but couldn't decide which one was yours as there are so many by your builder to choose from, are you at lock up yet?
Not yet. I'm the poor cousin in the middle of the 2 story and the Content one that's at lock up.[/quote]
Are you backing onto bush land with a funny shaped block, which gives you a huge back garden, none of your photos in photo bucket link work.[/quote]
Yep thats us. We are supposed to be down sizing on land and house but DH didn't want to go smaller than 520m2 and it was all that was available at the time as the sale had fallen through for the original buyers. So we have ended up on a larger lot, a triangle 628m2 but with a smaller house. The garden is going to be mostly pool, pavers and astroturf. I hate gardening.[/quote]
That's the one we wandered through to the back garden through your garage, hope you don't mind, looks good, we had garden envy, so did the dog
Love rear Master Bedrooms but couldn't manage it this time with our block/layout
Following
Love rear Master Bedrooms but couldn't manage it this time with our block/layout
Love rear Master Bedrooms but couldn't manage it this time with our block/layout
The plan doesn't show the best bit, patio door opens out onto spa area & day bed
Hi Druid1, slab down is great! Just a curious q - how long did it take the Council (joondalup) to approve your plans? I'm presuming that approval was sought after final plans on 1 July?
It only took 2 - 3 weeks for the permit to come through
Related
21/02/2024
7
Thank you so much everyone. This all makes a lot of sense. I guess when you talk to a builder who butters up everything to look very polished, you get to start believing…
10/06/2023
1
A person needs to be licensed to offer financial advice. Surely the accountant you use would have been chosen for his/her expertise in this field. Have you asked your…
20/07/2023
1
For reference, this is the Austlii reference. My take on this is, that they would be breaking the law denying access to a homeowner in Victoria, or their agent from having…