Regatta 2920 (Planbuild -Brisbane) - Handover complete :)

Page 1 of 12
I have noticed there have been a few threads asking for feedback on Planbuild homes. I was also searching for a comprehensive thread regarding the building experience with them whilst trying to decide on a builder - I really wish I had such a clear timeline and up to date dialogue on the building process.

We were quite frustrated to be stuck in admin land ... Now that we are onto the construction side of things, I thought it would benefit others to document our journey.

As such, I have decided to start my own thread to hopefully empower others to make informed decisions based upon my experience.

Timeline:
27/11/2013 - deposit on land & initial contact with Planbuild salesperson
20/12/2013 - land settled
16/01/2014 - Prelim agreement signed and initial deposit paid
6/02/2014 - Colour selection
13/03/2014 - Paid rest of 5% deposit
17/03/2014 - HIA contract signed
11/04/2014 - Council Approval
17/04/2014 - Lender Authority to Commence
07/05/2014 - Final selections signed off
09/05/2014 - Earthworks
10/05/2014 - Fence/gravel driveway
15/05/2014 - ready for slab
16/05/2014 - slab
21/05/2014 - lower storey frame
22/05/2014 - second storey frame
23/05/2014 - roof trusses
27/05/2014 - gutters and fascia
30/05/2014 - Colorbond roof (Upper roof)
04/06/2014 - Electrics/plumbing
05/06/2014 - Bricks started
16/06/2014 - Reached enclosed stage
20/06/2014 - Cladding/eaves complete
21/06/2014 - stairs
26/06/2014 - Kitchen/bathroom cabinetry. Exterior painting. Waterproofing.
30/06/2014 - Fixing Stage Complete
23/07/2014 - Plumbing complete, air con complete, electrical fit out
26/07/2014 - carpet, wardrobe doors, pantry shelves
28/07/2014 - clean & outdoor plumbing
29/07/2014 - Notice to book PCI
8/08/2014 - PCI @ 9am
14/08/2014 - Handover booked in for 1:30 pm
15/08/2014 - Handover complete
Moving tomorrow!
.
.
Have more photos coming, just need to download from camera.
.
Wow your house is looking good! It looks like tend are speeding along! When do they expect it to be finished?
We were told 16 weeks from slab, dsbuild -- so hopefully mid September
Ooh very nice Cinquain!

Any pictures of the plans? Or pictures of colour selections?
Upper roof stage (completed May 30)





We are building with Planbuild too, i will try to tie together our timeline.

Our timeline was subject to husband working away and Planbuild never working with his r&r schedule, so things were always 3-4 weeks delayed at a time.

28/10/2013 -Land deposit
5/12/2013 - Colour selections
11/12/2013 - Prelim agreement signed & Deposit to Planbuild
8/1/2014 - HIA Contract signed
7/2/2014 - Authority to commence construction
5/3/2014 - Land Settled
28/3/2014 - 5% Deposit paid
10/4/2014 - Council approval
21/4/2014 - signed off on final selections
22/4/2014 - letter of commencement
5/5/2014 - earthworks
8/5/2014 - slab
16/5/2014 - frame
20/5/2014 -roof trusses
23/5/2014 - gutter & fascia
27/5/2014 - roof
29/5/2014 - electrical & plumbing
30/5/2014 - plasterboard arrived
1/5/2014 - plasterboard on walls

Earthworks/plumbing for slab:


Slab:



Frame:



Roof Trusses:


Gutter & fascia:




Roof:



Electrical & Plumbing:


Plasterboard walls:






** Edited**
Enclosed stage due to be completed 4/6/14, was told by site supervisor on the 26/5/14 that there was a delay on the windows for our house and would be at least 2 days overdue.
Wednesday 3/6/14 - windows had been delivered and bricks delivered, Thursday 4/6/14 still no work on installing windows or bricks, however architraves were being installed.
EmyN
Ooh very nice Cinquain!

Any pictures of the plans? Or pictures of colour selections?


Lower floor plan:


Upper floor plan:


External elevations/colours:


Colorbond Evening Haze, Colorbond Gully, Colorbond Paperbark


Bricks will be Boral Stonewash with off-white mortar



Internal selections:

Floor tiles: Haven Charcoal 450 x 450
Wall tiles: Gloss White 300 x 450 (laid horizontally)

Cabinetry: Polytec Classic White Sheen
Benches in kitchen and ensuite: Caesarstone Walnut
Benches in main bath and laundry: Polytec Smokey Quartz



Carpet: Cyber grey
Paint: Solver Slightly

Drove by this afternoon, walls were wrapped and electricians on site. Bricks booked to start on Thursday


Great plans... house coming along nicely. This one is bigger then the beckham!

Yesterday's driveby. Lower roof finished. Plumbing being done and bricks delivered. Brickies due to start today


Windows in, bricks started, garage roof on.





Starting to question brick choice! Chose Boral stonewash with off-white mortar. Really hope the mortar dries a nice, lighter colour...

The block retaining wall between us and right-hand neighbours also got completed today, fence to go up next week, I think.
The mortar will dry lighter! Its look great!
Bricks Day 2.
I really, really hope that is off white mortar. It's looking very grey to me.
(Excuse crappy phone pics).



.
Great plans! I can't help with mortar sorry as ours is being painted. :s
Went out again today and mortar looks like it will dry lighter, double checked sand and cement.







Related
29/06/2023
0
Renovation/Extension at Auchenflower, Brisbane.

Renovation + Home Improvement

Hello Josh, This is Irving from PRIMA, we are a manufacturer of the staircase, railings, kitchen cabinets, windows, doors from China. If you have requirement to purchase…

30/06/2023
0
Certifier and the Brisbane development website

Building A New House

Hi, does anyone have a clue how the Brisbane Development website work in terms of how uptodate the dates on it are (developmenti.brisbane.qld.gov.au). I transfered…

7/06/2024
2
Omni built homes brisbane - builders feedback

General Discussion

Thanks , we decided to go with them now in the process of designing, yes I agree they are super flexible with design and super flexibility with our needs , anyway one…

You are here
Building ForumBuilding A New House
Home
Pros
Forum