KiwiGalAbroad's Build,Yanchep-PCI Done -Keys two weeks
Page 1 of 20
Hubby and I plus 4 kids are really excited to be building our first home. We have been living in Butler and like the Northern Suburbs so wanted to build near here, however the price of land has gone silly so we ended up where the budget would allow and have bought a 519m2 block in Yanchep. Hubby works in Joondalup so the drive to work will be a breeze down Wanneroo Rd.
We have chosen C.mmodo.e Homes and have been satisfied by the service so far. The titles on our block are due in two weeks so the site survey is currently being organised. Our plan is bits and pieces of the houses we liked the best, we started with The Challenger Plus and changed the kitchen/laundry to The Corsica and moved the activity . We then had to flip half the house so the living area is north facing, it now looks nothing like the original ! Will post plans once I work out how !
Time Line :
13/05/13 First contact with builder
23/05/13 First draft of plan
12/06/13 Sign land docs
26/06/13 Sign PWA
17/09/13 Early contracts
28/09/13 Finance Docs
24/10/13 Finance approval
29/10/13 Land practical completion
06/11/13 Land title issued
20/11/13 Settlement on land
20/12/13 Remaining Contracts
23/01/14 Tap
20/02/14 Prestart
10/03/14 Final Plans - v1
18/03/14 Final Plans - v2
14/04/14 Final Plans - v3
22/04/14 Final Plans - v4 Finally Correct !
29/04/14 Scheduling
14/05/14 Construction
23/05/14 Site Works (photos pg8 )
05/06/14 Slabbed !!
28/06/14 Bricks Delivered ( photo pg 11)
28/07/14 Brick work started
04/08/14 SS Meeting
10/09/14 Brick work finished
16/09/14 Roof Timber delivered
18/09/14 Roof Frame Started
03/10/14 Roof Frame Finished
03/10/14 Electrical & Plumbing
14/10/14 Colourbond (photos pg 16)
02/11/14 Grey Float completed
03/11/14 Ceilings Installed
04/11/14 Cornices and Ceiling plaster complete
06/11/14 Solar Hot Water Panels installed
17/11/14 White Float start
19/11/14 Front render done
20/11/14 White float completed
20/11/14 Doors Installed
21/11/14 Cupboard Shelves Installed
22/11/14 Bath Installed
24/11/14 Phone & Data
25/11/14 Windows ( LOCK UP)
02/12/14 Cabinets installed
05/12/14 Tiles delivered, Robe doors installed
09/12/14 Tile meeting
13/12/14 Tiling Started (wet areas)
16/12/14 Tiling Finished (wet areas), Basins installed, Ceilings painted
09/01/15 Concrete laid in Garage
27/01/15 Floor Tiles Finished
02/02/15 Painting completed
03/02/15 Paving
13/02/15 PCI booked
This is our design
Since this version was drawn we have added a linen cupboard to the back of the pantry, which made the entry to the study smaller and we have taken out the trough and linen in the laundry and added in a proper bench with sink and cupboards, wall cupboards and a broom cupboard.
Also the door on the WIR doesn't exist, it was drawn in the wrong place.
We got an email on the 31st Oct saying the block was at practical completion and that the titles would be approx the 18th Nov, so very pleased that they were this fast
Although I would be a bit delusional to think all things happen this fast
Have you had your pre-start yet? I asked about getting the pre-start info early but they told me they don't do that until the site inspection etc which I was a bit annoyed about but oh well!!
Wow that's a bugger about your titles , that would definitely do my head in !
We are just waiting for site survey, then contracts, then we can book our prestart ! That's the bit I've been waiting for
Ps
My DS always does his summer swimming lessons at the lagoon such a cool spor
Fantastic I built in clarkson 18 year ago (I would like to say I was 8 at the time lol) however back in the day we would take our 4wd through the end of Marmion Ave through pipindiny and still not reach Yanchep ......these days Marmion Abe goes straight to Yanchep and it's a suburb rather than outer country.....congratulations on your block.
Ps
My DS always does his summer swimming lessons at the lagoon such a cool spor
Ps
My DS always does his summer swimming lessons at the lagoon such a cool spor
Haha, yes we quite often have people tell us of the days when Yanchep was a day trip away. We are still discovering the area, and went to look at the lagoon last weekend, so pretty down there.
Well i often read about builders who have multiple staff changes and today I received a letter in the post from my builder, saying my pre-construction consultant had changed - I hope its the one and only change and not a sign .
Lol funny I got that same letter last month, although no idea who my pre-construction consultant was!! Also I was told the new one would contact me shortly to introduce herself and still haven't heard from her!!
Hubby thinks we should go pitch a tent on our section !!
Now to put up rocket up the builders bum and get them to hurry up !
Related
20/06/2023
1
The fastest thing a builder will do is bank your cheque, those systems work perfectly with lightning speed, everything else is slow burn. Just the way it is.
29/06/2023
0
Can someone please offer some advice? Im DESPERATE. Because I'm completely and utterly exhausted. How long are variations taking with other companies at the moment? We…
18/08/2023
6
We hired Darbecca to do every stage inspection, and I strongly recommend them to anyone that asks me. They were amazing. Thorough reports with photos at every stage,…