Our house is finally nearing practical completion. The builder asked me to get my Building Consultant in to do the final inspection next Friday. However, I am reluctant to do so as they haven't called Practical Completion....

So, did your Builder call Practical completion (and gave the 5 days required notice in writing) and then you got your building inspector in?

Or, did you get a final inspection done before practical completion was called?

Love to hear what is the "norm"

Thanks

K
I will be having a pre-pci with my own inspector 1 week before the actual pci.

Also, on the day of pci itself, my own inspector will be there beside me, so that the site supervisor can't tell me bulls***.
Thanks for your reply Zeitgeber. I cant help but think we are doing their Q.A!
Do you know if its normal to do it the way you (and I) are doing a pre-PCI inspection?
Can anyone else comment?
I just did the PCI on the appointed day.
Related
2/04/2024
1
Defects/Items found after final inspection

Building A New House

The significant date is when receive final payment invoice Check that section of contract Bit of fluff by builders prior to that

10/05/2024
3
Final Invoice and Key Handover

Building A New House

Hi Need to read your contract about when final payment is received. Clearly outlines what happens. In vic, known defects or incomplete work must be completed before…

24/11/2023
7
late completion penalty

Building A New House

Like I said the Occupancy Certificate is not the tollgate that marks the completion of the house. The contract defines…